Estimating and Costing The unit of measurement is per quintal for the following: Expanded metal wire netting Rolling shutters M.S. reinforcement of R.C.C. works Collapsible gates with rails Expanded metal wire netting Rolling shutters M.S. reinforcement of R.C.C. works Collapsible gates with rails ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3300 m³ 3225 m³ 3275 m³ 3250 m³ 3300 m³ 3225 m³ 3275 m³ 3250 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.90 m³ 0.94 m³ 1.00 m³ 0.98 m³ 0.90 m³ 0.94 m³ 1.00 m³ 0.98 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating a reinforced cement structure, the omitted cover of concrete is assumed All of these In thin slabs, 12 mm minimum or diameter of the bar whichever is more At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more All of these In thin slabs, 12 mm minimum or diameter of the bar whichever is more At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The main factor to be considered while preparing a detailed estimate, is All of these Transportation of materials Quantity of the materials Availability of materials All of these Transportation of materials Quantity of the materials Availability of materials ANSWER DOWNLOAD EXAMIANS APP