Estimating and Costing The unit of measurement is per quintal for the following: Rolling shutters Expanded metal wire netting Collapsible gates with rails M.S. reinforcement of R.C.C. works Rolling shutters Expanded metal wire netting Collapsible gates with rails M.S. reinforcement of R.C.C. works ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is L.D √(1 + s²) √[d² × (ds)²] 2 L.D √(1 + s²) d × d × s L.D √(1 + s²) √[d² × (ds)²] 2 L.D √(1 + s²) d × d × s ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called Master trap Intercepting trap Interception manhole All listed here Master trap Intercepting trap Interception manhole All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 5.0 m³ 1.5 m³ 2.5 m³ 3.5 m³ 5.0 m³ 1.5 m³ 2.5 m³ 3.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of All of these Excavation in trenches for foundation Rock cutting Earth work in excavation All of these Excavation in trenches for foundation Rock cutting Earth work in excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.04 0.02 0.05 0.025 0.04 0.02 0.05 0.025 ANSWER DOWNLOAD EXAMIANS APP