Estimating and Costing The unit of measurement is per quintal for the following: Rolling shutters Expanded metal wire netting Collapsible gates with rails M.S. reinforcement of R.C.C. works Rolling shutters Expanded metal wire netting Collapsible gates with rails M.S. reinforcement of R.C.C. works ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is B × d - Sd1/2 B + d + Sd Bd + Sd2 ½ (Bd + Sd2) B × d - Sd1/2 B + d + Sd Bd + Sd2 ½ (Bd + Sd2) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters Wall panels All of these Root slabs Floors Wall panels All of these Root slabs Floors ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 5.0 m³ 2.5 m³ 1.5 m³ 3.5 m³ 5.0 m³ 2.5 m³ 1.5 m³ 3.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item whose weight is added to the weight of respective item, is All listed here Bolts Cleats Brackets All listed here Bolts Cleats Brackets ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Cutting Surface excavation Excavation Surface dressing Cutting Surface excavation Excavation Surface dressing ANSWER DOWNLOAD EXAMIANS APP