Estimating and Costing The unit of measurement is per quintal for the following: Rolling shutters Collapsible gates with rails M.S. reinforcement of R.C.C. works Expanded metal wire netting Rolling shutters Collapsible gates with rails M.S. reinforcement of R.C.C. works Expanded metal wire netting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 1.00 cum 3.00 cum 4.00 cum 2.00 cum 1.00 cum 3.00 cum 4.00 cum 2.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Size, capacity and materials need be specified for Stop-cocks Bib-cocks All of these Ball valves Stop-cocks Bib-cocks All of these Ball valves ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The most reliable estimate is Cube rate estimate Detailed estimate Plinth area estimate Preliminary estimate Cube rate estimate Detailed estimate Plinth area estimate Preliminary estimate ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Setting out of works All listed here Steps in deep excavation Site clearance Setting out of works All listed here Steps in deep excavation Site clearance ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 30 D 59 D 39 D 50 D 30 D 59 D 39 D 50 D ANSWER DOWNLOAD EXAMIANS APP