Estimating and Costing Cost of fittings and their fixing is specified for the following sanitary fittings Flushing pipes Lavatory basins Water closets All listed here Flushing pipes Lavatory basins Water closets All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,000 m³ 26,500 m³ 27,500 m³ 27,000 m³ 26,000 m³ 26,500 m³ 27,500 m³ 27,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.02 0.05 0.04 0.025 0.02 0.05 0.04 0.025 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.274 m³ 0.295 m³ 0.247 m³ 0.200 m³ 0.274 m³ 0.295 m³ 0.247 m³ 0.200 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Dimension should be measured correct to 0.01 m Volume should be measured correct to 0.01 cum All of these Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m Volume should be measured correct to 0.01 cum All of these Area should be measured correct to 0.01 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system At every change of direction At every change of gradient All of these At every 30 m intervals At every change of direction At every change of gradient All of these At every 30 m intervals ANSWER DOWNLOAD EXAMIANS APP