Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.247 m³ 0.200 m³ 0.295 m³ 0.274 m³ 0.247 m³ 0.200 m³ 0.295 m³ 0.274 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system At every 30 m intervals All of these At every change of direction At every change of gradient At every 30 m intervals All of these At every change of direction At every change of gradient ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.04 cum 0.02 cum 0.01 cum 0.03 cum 0.04 cum 0.02 cum 0.01 cum 0.03 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: Length of long wall out-to-out is 6.80 m The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m All listed here Length of long wall out-to-out is 6.80 m The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 7.5 sqm 10 sqm 5.0 sqm 2.5 sqm 7.5 sqm 10 sqm 5.0 sqm 2.5 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The order of booking dimensions is Breadth, length, height Height, breadth, length None of these Length, breadth, height Breadth, length, height Height, breadth, length None of these Length, breadth, height ANSWER DOWNLOAD EXAMIANS APP