Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.295 m³ 0.247 m³ 0.200 m³ 0.274 m³ 0.295 m³ 0.247 m³ 0.200 m³ 0.274 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is 20 cm 10 cm None of these 15 cm 20 cm 10 cm None of these 15 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 12° 8° 10° 14° 12° 8° 10° 14° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes All of these Connection to drains Setting and laying Bed concreting All of these Connection to drains Setting and laying Bed concreting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3225 m³ 3275 m³ 3250 m³ 3300 m³ 3225 m³ 3275 m³ 3250 m³ 3300 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is L.D √(1 + s²) 2 L.D √(1 + s²) √[d² × (ds)²] d × d × s L.D √(1 + s²) 2 L.D √(1 + s²) √[d² × (ds)²] d × d × s ANSWER DOWNLOAD EXAMIANS APP