Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Surface dressing Cutting Surface excavation Excavation Surface dressing Cutting Surface excavation Excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3300 m³ 3275 m³ 3250 m³ 3225 m³ 3300 m³ 3275 m³ 3250 m³ 3225 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item whose weight is added to the weight of respective item, is Brackets All listed here Cleats Bolts Brackets All listed here Cleats Bolts ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.03 cum 0.04 cum 0.01 cum 0.02 cum 0.03 cum 0.04 cum 0.01 cum 0.02 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Earth work in excavation All of these Rock cutting Excavation in trenches for foundation Earth work in excavation All of these Rock cutting Excavation in trenches for foundation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The area of mid-sections is calculated by using mean depth All of these The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The area of mid-sections is calculated by using mean depth All of these ANSWER DOWNLOAD EXAMIANS APP