Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Excavation Surface excavation Surface dressing Cutting Excavation Surface excavation Surface dressing Cutting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 2.5 sqm 7.5 sqm 5.0 sqm 10 sqm 2.5 sqm 7.5 sqm 5.0 sqm 10 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are Partly in excavation and partly in embankment Fully in embankment Fully in excavation All of these Partly in excavation and partly in embankment Fully in embankment Fully in excavation All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and Breadth of the wall One fourth breadth of wall on each side None of these Half breadth of wall on each side Breadth of the wall One fourth breadth of wall on each side None of these Half breadth of wall on each side ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters Wall panels Root slabs All of these Floors Wall panels Root slabs All of these Floors ANSWER DOWNLOAD EXAMIANS APP