Estimating and Costing The assumption on which the trapezoidal formula for volumes is based, is All listed here The mid-area of a pyramid is half the average area of the ends The end sections are parallel planes The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied All listed here The mid-area of a pyramid is half the average area of the ends The end sections are parallel planes The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.295 m³ 0.200 m³ 0.247 m³ 0.274 m³ 0.295 m³ 0.200 m³ 0.247 m³ 0.274 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Excavation in trenches for foundation Earth work in excavation All of these Rock cutting Excavation in trenches for foundation Earth work in excavation All of these Rock cutting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 3.5 m³ 5.0 m³ 2.5 m³ 1.5 m³ 3.5 m³ 5.0 m³ 2.5 m³ 1.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The plinth area of a building not includes Internal shaft for sanitary installations up to 2 sq m. in area Area of cantilevered porch Lift and wall including landing Area of the walls at the floor level Internal shaft for sanitary installations up to 2 sq m. in area Area of cantilevered porch Lift and wall including landing Area of the walls at the floor level ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Cutting Surface dressing Surface excavation Excavation Cutting Surface dressing Surface excavation Excavation ANSWER DOWNLOAD EXAMIANS APP