Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Square meters for volume Meter for length Liter for capacity Cubic metre for area Square meters for volume Meter for length Liter for capacity Cubic metre for area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 0.25 0.5 0.75 1 0.25 0.5 0.75 1 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The correct Prismoidal formula for volume is D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 50 D 30 D 39 D 59 D 50 D 30 D 39 D 59 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is measured in sq metre, in case of Brick flat soling Honey comb brick work All of these Half brick walls or the partition Brick flat soling Honey comb brick work All of these Half brick walls or the partition ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is L - (2 × 0.4 d) L + (2 × 0.42 d) L - (0.42 d) L + 0.42 d L - (2 × 0.4 d) L + (2 × 0.42 d) L - (0.42 d) L + 0.42 d ANSWER DOWNLOAD EXAMIANS APP