Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Square meters for volume Liter for capacity Cubic metre for area Meter for length Square meters for volume Liter for capacity Cubic metre for area Meter for length ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.274 m³ 0.200 m³ 0.295 m³ 0.247 m³ 0.274 m³ 0.200 m³ 0.295 m³ 0.247 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,500 m³ 26,000 m³ 27,500 m³ 27,000 m³ 26,500 m³ 26,000 m³ 27,500 m³ 27,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing All of these Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is L - (2 × 0.4 d) L - (0.42 d) L + (2 × 0.42 d) L + 0.42 d L - (2 × 0.4 d) L - (0.42 d) L + (2 × 0.42 d) L + 0.42 d ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is Bd + Sd2 ½ (Bd + Sd2) B × d - Sd1/2 B + d + Sd Bd + Sd2 ½ (Bd + Sd2) B × d - Sd1/2 B + d + Sd ANSWER DOWNLOAD EXAMIANS APP