Estimating and Costing The floor area includes the area of the balcony up to 1 0.25 0.5 0.75 1 0.25 0.5 0.75 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 14° 8° 10° 12° 14° 8° 10° 12° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to ISI method of measurement, the order of the sequence is Length, breadth, height Breadth, length, height None of these Height, length, breadth Length, breadth, height Breadth, length, height None of these Height, length, breadth ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The plinth area of a building not includes Lift and wall including landing Area of the walls at the floor level Internal shaft for sanitary installations up to 2 sq m. in area Area of cantilevered porch Lift and wall including landing Area of the walls at the floor level Internal shaft for sanitary installations up to 2 sq m. in area Area of cantilevered porch ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3250 m³ 3300 m³ 3225 m³ 3275 m³ 3250 m³ 3300 m³ 3225 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth ANSWER DOWNLOAD EXAMIANS APP