Estimating and Costing The floor area includes the area of the balcony up to 0.25 1 0.75 0.5 0.25 1 0.75 0.5 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Site clearance Setting out of works Steps in deep excavation All listed here Site clearance Setting out of works Steps in deep excavation All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating a reinforced cement structure, the omitted cover of concrete is assumed For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar In thin slabs, 12 mm minimum or diameter of the bar whichever is more All of these For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar In thin slabs, 12 mm minimum or diameter of the bar whichever is more All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.295 m³ 0.200 m³ 0.247 m³ 0.274 m³ 0.295 m³ 0.200 m³ 0.247 m³ 0.274 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken 1.80 liters for 5 to 10 users 1.35 for 20 users 1.20 liters for 15 users All of these 1.80 liters for 5 to 10 users 1.35 for 20 users 1.20 liters for 15 users All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Size, capacity and materials need be specified for Stop-cocks Ball valves All of these Bib-cocks Stop-cocks Ball valves All of these Bib-cocks ANSWER DOWNLOAD EXAMIANS APP