Estimating and Costing The floor area includes the area of the balcony up to 1 0.5 0.75 0.25 1 0.5 0.75 0.25 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 18) chains None of these (6 + 12) chains (6 + 15) chains (6 + 18) chains None of these (6 + 12) chains (6 + 15) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 8° 10° 14° 12° 8° 10° 14° 12° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.75 m³ 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ 1.25 m³ 1.50 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-sections for a highway is taken at Intermediate points having abrupt change in gradient All of these Right angle to the centre line 30 meters apart Intermediate points having abrupt change in gradient All of these Right angle to the centre line 30 meters apart ANSWER DOWNLOAD EXAMIANS APP