Estimating and Costing The brick work is not measured in cu m in case of Brick work in arches One or more than one brick wall Half brick wall Reinforced brick work Brick work in arches One or more than one brick wall Half brick wall Reinforced brick work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 15) chains (6 + 18) chains (6 + 12) chains None of these (6 + 15) chains (6 + 18) chains (6 + 12) chains None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.98 m³ 0.90 m³ 1.00 m³ 0.94 m³ 0.98 m³ 0.90 m³ 1.00 m³ 0.94 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on Proportion of mortar Specifications of works Specifications of materials All of these Proportion of mortar Specifications of works Specifications of materials All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 8° 14° 12° 10° 8° 14° 12° 10° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken All of these 1.20 liters for 15 users 1.80 liters for 5 to 10 users 1.35 for 20 users All of these 1.20 liters for 15 users 1.80 liters for 5 to 10 users 1.35 for 20 users ANSWER DOWNLOAD EXAMIANS APP