Estimating and Costing The brick work is not measured in cu m in case of One or more than one brick wall Reinforced brick work Half brick wall Brick work in arches One or more than one brick wall Reinforced brick work Half brick wall Brick work in arches ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The plinth area of a building not includes Area of the walls at the floor level Area of cantilevered porch Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing Area of the walls at the floor level Area of cantilevered porch Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Size, capacity and materials need be specified for Stop-cocks Ball valves All of these Bib-cocks Stop-cocks Ball valves All of these Bib-cocks ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The detention period in a septic tank is assumed 40 minutes 25 minutes 20 minutes 30 minutes 40 minutes 25 minutes 20 minutes 30 minutes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.01 cum 0.02 cum 0.04 cum 0.03 cum 0.01 cum 0.02 cum 0.04 cum 0.03 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these ANSWER DOWNLOAD EXAMIANS APP