Estimating and Costing The brick work is not measured in cu m in case of Half brick wall Reinforced brick work Brick work in arches One or more than one brick wall Half brick wall Reinforced brick work Brick work in arches One or more than one brick wall ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 5.0 m2 1.5 m2 4.0 m2 2.0 m2 5.0 m2 1.5 m2 4.0 m2 2.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made in square metre in case of R.C.C. structure Hollow concrete block wall Cement concrete in foundation None of these R.C.C. structure Hollow concrete block wall Cement concrete in foundation None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to ISI method of measurement, the order of the sequence is Breadth, length, height None of these Length, breadth, height Height, length, breadth Breadth, length, height None of these Length, breadth, height Height, length, breadth ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is measured in sq metre, in case of Honey comb brick work Brick flat soling All of these Half brick walls or the partition Honey comb brick work Brick flat soling All of these Half brick walls or the partition ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item of work not included in the plinth area estimate Courtyard area W' Area Wall thickness Room area Courtyard area W' Area Wall thickness Room area ANSWER DOWNLOAD EXAMIANS APP