Estimating and Costing Size, capacity and materials need be specified for Bib-cocks Stop-cocks All of these Ball valves Bib-cocks Stop-cocks All of these Ball valves ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Setting out of works Steps in deep excavation Site clearance All listed here Setting out of works Steps in deep excavation Site clearance All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3250 m³ 3225 m³ 3300 m³ 3275 m³ 3250 m³ 3225 m³ 3300 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 1.5 m2 2.0 m2 5.0 m2 4.0 m2 1.5 m2 2.0 m2 5.0 m2 4.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item whose weight is added to the weight of respective item, is Bolts Cleats All listed here Brackets Bolts Cleats All listed here Brackets ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.02 cum 0.04 cum 0.01 cum 0.03 cum 0.02 cum 0.04 cum 0.01 cum 0.03 cum ANSWER DOWNLOAD EXAMIANS APP