Estimating and Costing Size, capacity and materials need be specified for Ball valves Bib-cocks All of these Stop-cocks Ball valves Bib-cocks All of these Stop-cocks ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the incorrect statement regarding a master trap from the following: It is provided a cleaning eye at the top of the trap The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe It is provided in between the lower end of the house drain and the street sewer The water seal is less than that of ordinary traps It is provided a cleaning eye at the top of the trap The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe It is provided in between the lower end of the house drain and the street sewer The water seal is less than that of ordinary traps ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 1.00 m³ 0.98 m³ 0.94 m³ 0.90 m³ 1.00 m³ 0.98 m³ 0.94 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 60 cm 80 cm 75 cm to 80 cm 70 cm 60 cm 80 cm 75 cm to 80 cm 70 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.02 cum 0.04 cum 0.01 cum 0.03 cum 0.02 cum 0.04 cum 0.01 cum 0.03 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Main soil pipe Top of P trap W.C. Bottom of P trap W.C. Side of water closet Main soil pipe Top of P trap W.C. Bottom of P trap W.C. Side of water closet ANSWER DOWNLOAD EXAMIANS APP