Estimating and Costing Size, capacity and materials need be specified for Stop-cocks Ball valves Bib-cocks All of these Stop-cocks Ball valves Bib-cocks All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Rock cutting All of these Earth work in excavation Excavation in trenches for foundation Rock cutting All of these Earth work in excavation Excavation in trenches for foundation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are All of these Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing All of these Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of the brick structure measured in sq.m, is Reinforced brick work Broken glass coping Brick edging Brick work in arches Reinforced brick work Broken glass coping Brick edging Brick work in arches ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 50 D 59 D 39 D 30 D 50 D 59 D 39 D 30 D ANSWER DOWNLOAD EXAMIANS APP