Estimating and Costing
Size, capacity and materials need be specified for

Stop-cocks
Ball valves
Bib-cocks
All of these

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The rate of payment is made for 100 cu m (per % cu m) in case of

Rock cutting
All of these
Earth work in excavation
Excavation in trenches for foundation

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
For the construction of buildings, the subheads of the estimate are

All of these
Brickwork Flooring, Wood work, Steel work
Earthwork, Concrete work, Brick work
Brickwork, Stone work, Roofing

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The item of the brick structure measured in sq.m, is

Reinforced brick work
Broken glass coping
Brick edging
Brick work in arches

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is

⅓ × (b - rd)²/(r + s)
⅓ × (b - rd)²/(s - r)
⅓ × (b - rd)²/(r - s)
½ × (b + rd)²/(r - s)

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is

50 D
59 D
39 D
30 D

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Estimating and Costing

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑