Estimating and Costing The brick work is measured in sq metre, in case of All of these Honey comb brick work Brick flat soling Half brick walls or the partition All of these Honey comb brick work Brick flat soling Half brick walls or the partition ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 3.00 cum 1.00 cum 2.00 cum 4.00 cum 3.00 cum 1.00 cum 2.00 cum 4.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of the brick structure measured in sq.m, is Brick work in arches Broken glass coping Reinforced brick work Brick edging Brick work in arches Broken glass coping Reinforced brick work Brick edging ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.04 0.05 0.025 0.02 0.04 0.05 0.025 0.02 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is not measured in cu m in case of Brick work in arches Reinforced brick work One or more than one brick wall Half brick wall Brick work in arches Reinforced brick work One or more than one brick wall Half brick wall ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. Pipes are classified according to their sizes and quality Cutting through walls and floors are included with the item All of these Pipes laid in trenches and pipes fixed to walls are measured separately Pipes are classified according to their sizes and quality Cutting through walls and floors are included with the item All of these Pipes laid in trenches and pipes fixed to walls are measured separately ANSWER DOWNLOAD EXAMIANS APP