Estimating and Costing
The brick work is measured in sq metre, in case of

Half brick walls or the partition
Honey comb brick work
Brick flat soling
All of these

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
In the mid-section formula

The mean depth is the average of depths of two consecutive sections
All of these
The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections
The area of mid-sections is calculated by using mean depth

ANSWER DOWNLOAD EXAMIANS APP