Estimating and Costing The 'centre line method' is specially adopted for estimating Circular buildings Hexagonal buildings All of these Octagonal buildings Circular buildings Hexagonal buildings All of these Octagonal buildings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The unit of measurement is per quintal for the following: Collapsible gates with rails Expanded metal wire netting M.S. reinforcement of R.C.C. works Rolling shutters Collapsible gates with rails Expanded metal wire netting M.S. reinforcement of R.C.C. works Rolling shutters ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing All of these Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing All of these Brickwork Flooring, Wood work, Steel work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. Pipes laid in trenches and pipes fixed to walls are measured separately All of these Cutting through walls and floors are included with the item Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately All of these Cutting through walls and floors are included with the item Pipes are classified according to their sizes and quality ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 0.25 0.75 1 0.5 0.25 0.75 1 0.5 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 3.5 m³ 2.5 m³ 5.0 m³ 1.5 m³ 3.5 m³ 2.5 m³ 5.0 m³ 1.5 m³ ANSWER DOWNLOAD EXAMIANS APP