Estimating and Costing The 'centre line method' is specially adopted for estimating Circular buildings Octagonal buildings All of these Hexagonal buildings Circular buildings Octagonal buildings All of these Hexagonal buildings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,500 m³ 26,500 m³ 26,000 m³ 27,000 m³ 27,500 m³ 26,500 m³ 26,000 m³ 27,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is 2 L.D √(1 + s²) L.D √(1 + s²) √[d² × (ds)²] d × d × s 2 L.D √(1 + s²) L.D √(1 + s²) √[d² × (ds)²] d × d × s ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 2.5 m³ 5.0 m³ 3.5 m³ 1.5 m³ 2.5 m³ 5.0 m³ 3.5 m³ 1.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Bed concreting All of these Setting and laying Connection to drains Bed concreting All of these Setting and laying Connection to drains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is not measured in cu m in case of Half brick wall Reinforced brick work One or more than one brick wall Brick work in arches Half brick wall Reinforced brick work One or more than one brick wall Brick work in arches ANSWER DOWNLOAD EXAMIANS APP