Estimating and Costing The 'centre line method' is specially adopted for estimating Circular buildings Octagonal buildings Hexagonal buildings All of these Circular buildings Octagonal buildings Hexagonal buildings All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-sections for a highway is taken at Right angle to the centre line Intermediate points having abrupt change in gradient All of these 30 meters apart Right angle to the centre line Intermediate points having abrupt change in gradient All of these 30 meters apart ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 1.5 m³ 2.5 m³ 5.0 m³ 3.5 m³ 1.5 m³ 2.5 m³ 5.0 m³ 3.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item Pipes are classified according to their sizes and quality All of these Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item Pipes are classified according to their sizes and quality All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 1.00 m³ 0.94 m³ 0.98 m³ 0.90 m³ 1.00 m³ 0.94 m³ 0.98 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Setting and laying Bed concreting Connection to drains All of these Setting and laying Bed concreting Connection to drains All of these ANSWER DOWNLOAD EXAMIANS APP