Estimating and Costing For the construction of buildings, the subheads of the estimate are Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work All of these Brickwork, Stone work, Roofing Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work All of these Brickwork, Stone work, Roofing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: Length of short walls in-to-in is 3.20 m The total length of centre line of four walls is 20 m Length of long wall out-to-out is 6.80 m All listed here Length of short walls in-to-in is 3.20 m The total length of centre line of four walls is 20 m Length of long wall out-to-out is 6.80 m All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.75 m³ 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ 1.25 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of All of these Rock cutting Excavation in trenches for foundation Earth work in excavation All of these Rock cutting Excavation in trenches for foundation Earth work in excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 0.5 0.25 1 0.75 0.5 0.25 1 0.75 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Bed concreting Setting and laying Connection to drains All of these Bed concreting Setting and laying Connection to drains All of these ANSWER DOWNLOAD EXAMIANS APP