Estimating and Costing For the construction of buildings, the subheads of the estimate are Brickwork, Stone work, Roofing Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work All of these Brickwork, Stone work, Roofing Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.75 kg 1.00 kg 0.50 kg 0.25 kg 0.75 kg 1.00 kg 0.50 kg 0.25 kg ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Size, capacity and materials need be specified for Stop-cocks Ball valves Bib-cocks All of these Stop-cocks Ball valves Bib-cocks All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 75 cm to 80 cm 80 cm 60 cm 70 cm 75 cm to 80 cm 80 cm 60 cm 70 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 14° 10° 12° 8° 14° 10° 12° 8° ANSWER DOWNLOAD EXAMIANS APP