Estimating and Costing For the construction of buildings, the subheads of the estimate are Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing All of these Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work Brickwork, Stone work, Roofing All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The plinth area of a building not includes Area of the walls at the floor level Lift and wall including landing Area of cantilevered porch Internal shaft for sanitary installations up to 2 sq m. in area Area of the walls at the floor level Lift and wall including landing Area of cantilevered porch Internal shaft for sanitary installations up to 2 sq m. in area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are Partly in excavation and partly in embankment Fully in excavation All of these Fully in embankment Partly in excavation and partly in embankment Fully in excavation All of these Fully in embankment ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made for stone work in square metre in case of Columns, lintels, copings Wall facing (A) and (B) of the above Building work Columns, lintels, copings Wall facing (A) and (B) of the above Building work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 12° 8° 10° 14° 12° 8° 10° 14° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,000 m³ 26,500 m³ 27,000 m³ 27,500 m³ 26,000 m³ 26,500 m³ 27,000 m³ 27,500 m³ ANSWER DOWNLOAD EXAMIANS APP