Estimating and Costing The trap which is provided to disconnect the house drain from the street sewer is called All listed here Intercepting trap Master trap Interception manhole All listed here Intercepting trap Master trap Interception manhole ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building The centre line length is reduced by half the layer of main wall joining the partition wall All of these The centre line is worked out separately for different sections of walls of a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line length is reduced by half the layer of main wall joining the partition wall All of these The centre line is worked out separately for different sections of walls of a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-sections for a highway is taken at 30 meters apart Intermediate points having abrupt change in gradient Right angle to the centre line All of these 30 meters apart Intermediate points having abrupt change in gradient Right angle to the centre line All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of All of these Earth work in excavation Excavation in trenches for foundation Rock cutting All of these Earth work in excavation Excavation in trenches for foundation Rock cutting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The minimum width of a septic tank is taken 80 cm 90 cm 75 cm 70 cm 80 cm 90 cm 75 cm 70 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.025 0.02 0.05 0.04 0.025 0.02 0.05 0.04 ANSWER DOWNLOAD EXAMIANS APP