Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 5.0 sqm 2.5 sqm 10 sqm 7.5 sqm 5.0 sqm 2.5 sqm 10 sqm 7.5 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: Length of short walls in-to-in is 3.20 m All listed here The total length of centre line of four walls is 20 m Length of long wall out-to-out is 6.80 m Length of short walls in-to-in is 3.20 m All listed here The total length of centre line of four walls is 20 m Length of long wall out-to-out is 6.80 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 3.5 m³ 5.0 m³ 2.5 m³ 1.5 m³ 3.5 m³ 5.0 m³ 2.5 m³ 1.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Area should be measured correct to 0.01 sqm All of these Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm All of these Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Surface excavation Cutting Excavation Surface dressing Surface excavation Cutting Excavation Surface dressing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.05 0.02 0.025 0.04 0.05 0.02 0.025 0.04 ANSWER DOWNLOAD EXAMIANS APP