Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 10 sqm 5.0 sqm 2.5 sqm 7.5 sqm 10 sqm 5.0 sqm 2.5 sqm 7.5 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.200 m³ 0.274 m³ 0.295 m³ 0.247 m³ 0.200 m³ 0.274 m³ 0.295 m³ 0.247 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The damp proof course (D.P.C.) is measured in Meters Cub. m Sq. m None of these Meters Cub. m Sq. m None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and One fourth breadth of wall on each side Breadth of the wall Half breadth of wall on each side None of these One fourth breadth of wall on each side Breadth of the wall Half breadth of wall on each side None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 3.00 cum 2.00 cum 1.00 cum 4.00 cum 3.00 cum 2.00 cum 1.00 cum 4.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The detention period in a septic tank is assumed 20 minutes 30 minutes 25 minutes 40 minutes 20 minutes 30 minutes 25 minutes 40 minutes ANSWER DOWNLOAD EXAMIANS APP