Estimating and Costing Pick up the item of work not included in the plinth area estimate Wall thickness W' Area Room area Courtyard area Wall thickness W' Area Room area Courtyard area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on All of these Specifications of materials Proportion of mortar Specifications of works All of these Specifications of materials Proportion of mortar Specifications of works ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of the brick structure measured in sq.m, is Brick edging Reinforced brick work Brick work in arches Broken glass coping Brick edging Reinforced brick work Brick work in arches Broken glass coping ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The assumption on which the trapezoidal formula for volumes is based, is The end sections are parallel planes The mid-area of a pyramid is half the average area of the ends The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied All listed here The end sections are parallel planes The mid-area of a pyramid is half the average area of the ends The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is d × d × s L.D √(1 + s²) 2 L.D √(1 + s²) √[d² × (ds)²] d × d × s L.D √(1 + s²) 2 L.D √(1 + s²) √[d² × (ds)²] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,000 m³ 27,500 m³ 27,000 m³ 26,500 m³ 26,000 m³ 27,500 m³ 27,000 m³ 26,500 m³ ANSWER DOWNLOAD EXAMIANS APP