Estimating and Costing

Estimating and Costing
Pick up the item of work not included in the plinth area estimate

Room area
Courtyard area
W' Area
Wall thickness

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The following item of earth work is not measured separately.

Steps in deep excavation
Setting out of works
Site clearance
All listed here

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

5.0 m³
2.5 m³
3.5 m³
1.5 m³

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is

B + d + Sd
B × d - Sd1/2
½ (Bd + Sd2)
Bd + Sd2

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
Berms are provided in canals if these are

Fully in embankment
Partly in excavation and partly in embankment
Fully in excavation
All of these

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
For the construction of buildings, the subheads of the estimate are

Earthwork, Concrete work, Brick work
Brickwork Flooring, Wood work, Steel work
All of these
Brickwork, Stone work, Roofing

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Estimating and Costing

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑