Estimating and Costing Pick up the item of work not included in the plinth area estimate W' Area Courtyard area Room area Wall thickness W' Area Courtyard area Room area Wall thickness ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Excavation in trenches for foundation Earth work in excavation Rock cutting All of these Excavation in trenches for foundation Earth work in excavation Rock cutting All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is 10 cm 20 cm None of these 15 cm 10 cm 20 cm None of these 15 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.274 m³ 0.200 m³ 0.247 m³ 0.295 m³ 0.274 m³ 0.200 m³ 0.247 m³ 0.295 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The main factor to be considered while preparing a detailed estimate, is Quantity of the materials All of these Transportation of materials Availability of materials Quantity of the materials All of these Transportation of materials Availability of materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 15) chains (6 + 18) chains None of these (6 + 12) chains (6 + 15) chains (6 + 18) chains None of these (6 + 12) chains ANSWER DOWNLOAD EXAMIANS APP