Estimating and Costing

Estimating and Costing
Pick up the item of work not included in the plinth area estimate

W' Area
Wall thickness
Courtyard area
Room area

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The plinth area of a building not includes

Area of cantilevered porch
Area of the walls at the floor level
Lift and wall including landing
Internal shaft for sanitary installations up to 2 sq m. in area

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is

(6 + 15) chains
None of these
(6 + 18) chains
(6 + 12) chains

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The expected out turn of 2.5 cm cement concrete floor per mansion per day

7.5 sqm
2.5 sqm
5.0 sqm
10 sqm

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The measurement is not made in square meters in case of

P.C. (Damp proof course)
Form works
R.C. Chhajja
Concrete Jeffries

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The weight of an item is measured correct to nearest

0.75 kg
1.00 kg
0.25 kg
0.50 kg

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Estimating and Costing

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑