Estimating and Costing Pick up the item of work not included in the plinth area estimate Wall thickness W' Area Room area Courtyard area Wall thickness W' Area Room area Courtyard area ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The minimum width of a septic tank is taken 90 cm 75 cm 80 cm 70 cm 90 cm 75 cm 80 cm 70 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area is measured correct to the nearest 0.01 sqm 0.04 sqm 0.03 sqm 0.02 sqm 0.01 sqm 0.04 sqm 0.03 sqm 0.02 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Square meters for volume Cubic metre for area Meter for length Liter for capacity Square meters for volume Cubic metre for area Meter for length Liter for capacity ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 5.0 m2 2.0 m2 1.5 m2 4.0 m2 5.0 m2 2.0 m2 1.5 m2 4.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating a reinforced cement structure, the omitted cover of concrete is assumed At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar In thin slabs, 12 mm minimum or diameter of the bar whichever is more For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more All of these At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar In thin slabs, 12 mm minimum or diameter of the bar whichever is more For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more All of these ANSWER DOWNLOAD EXAMIANS APP