Estimating and Costing The cross-sections for a highway is taken at All of these 30 meters apart Intermediate points having abrupt change in gradient Right angle to the centre line All of these 30 meters apart Intermediate points having abrupt change in gradient Right angle to the centre line ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 5.0 m³ 2.5 m³ 3.5 m³ 1.5 m³ 5.0 m³ 2.5 m³ 3.5 m³ 1.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is √[d² × (ds)²] L.D √(1 + s²) d × d × s 2 L.D √(1 + s²) √[d² × (ds)²] L.D √(1 + s²) d × d × s 2 L.D √(1 + s²) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: Length of short walls in-to-in is 3.20 m Length of long wall out-to-out is 6.80 m All listed here The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m Length of long wall out-to-out is 6.80 m All listed here The total length of centre line of four walls is 20 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 1.00 cum 2.00 cum 3.00 cum 4.00 cum 1.00 cum 2.00 cum 3.00 cum 4.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.25 kg 0.75 kg 0.50 kg 1.00 kg 0.25 kg 0.75 kg 0.50 kg 1.00 kg ANSWER DOWNLOAD EXAMIANS APP