Estimating and Costing The cross-sections for a highway is taken at 30 meters apart Right angle to the centre line Intermediate points having abrupt change in gradient All of these 30 meters apart Right angle to the centre line Intermediate points having abrupt change in gradient All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are Brickwork, Stone work, Roofing Earthwork, Concrete work, Brick work All of these Brickwork Flooring, Wood work, Steel work Brickwork, Stone work, Roofing Earthwork, Concrete work, Brick work All of these Brickwork Flooring, Wood work, Steel work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of an item of work depends on Proportion of mortar Specifications of works All of these Specifications of materials Proportion of mortar Specifications of works All of these Specifications of materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. All of these Pipes are classified according to their sizes and quality Cutting through walls and floors are included with the item Pipes laid in trenches and pipes fixed to walls are measured separately All of these Pipes are classified according to their sizes and quality Cutting through walls and floors are included with the item Pipes laid in trenches and pipes fixed to walls are measured separately ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.98 m³ 0.90 m³ 1.00 m³ 0.94 m³ 0.98 m³ 0.90 m³ 1.00 m³ 0.94 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 59 D 30 D 50 D 39 D 59 D 30 D 50 D 39 D ANSWER DOWNLOAD EXAMIANS APP