Estimating and Costing The volume is measured correct to the nearest 0.04 cum 0.01 cum 0.02 cum 0.03 cum 0.04 cum 0.01 cum 0.02 cum 0.03 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.90 m³ 0.98 m³ 0.94 m³ 1.00 m³ 0.90 m³ 0.98 m³ 0.94 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The detention period in a septic tank is assumed 25 minutes 30 minutes 40 minutes 20 minutes 25 minutes 30 minutes 40 minutes 20 minutes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Bottom of P trap W.C. Main soil pipe Top of P trap W.C. Side of water closet Bottom of P trap W.C. Main soil pipe Top of P trap W.C. Side of water closet ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is d × d × s L.D √(1 + s²) 2 L.D √(1 + s²) √[d² × (ds)²] d × d × s L.D √(1 + s²) 2 L.D √(1 + s²) √[d² × (ds)²] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The mean depth is the average of depths of two consecutive sections ANSWER DOWNLOAD EXAMIANS APP