Estimating and Costing The volume is measured correct to the nearest 0.02 cum 0.03 cum 0.04 cum 0.01 cum 0.02 cum 0.03 cum 0.04 cum 0.01 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 6.0 sq m 2.5 sq m 4.0 sq m 8.0 sq m 6.0 sq m 2.5 sq m 4.0 sq m 8.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m All listed here Length of long wall out-to-out is 6.80 m The total length of centre line of four walls is 20 m Length of short walls in-to-in is 3.20 m All listed here Length of long wall out-to-out is 6.80 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 3.5 m³ 5.0 m³ 2.5 m³ 1.5 m³ 3.5 m³ 5.0 m³ 2.5 m³ 1.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3300 m³ 3225 m³ 3275 m³ 3250 m³ 3300 m³ 3225 m³ 3275 m³ 3250 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.98 m³ 0.94 m³ 1.00 m³ 0.90 m³ 0.98 m³ 0.94 m³ 1.00 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP