Estimating and Costing The volume is measured correct to the nearest 0.01 cum 0.03 cum 0.02 cum 0.04 cum 0.01 cum 0.03 cum 0.02 cum 0.04 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3225 m³ 3300 m³ 3250 m³ 3275 m³ 3225 m³ 3300 m³ 3250 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,500 m³ 26,000 m³ 27,000 m³ 26,500 m³ 27,500 m³ 26,000 m³ 27,000 m³ 26,500 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The main factor to be considered while preparing a detailed estimate, is Transportation of materials Availability of materials All of these Quantity of the materials Transportation of materials Availability of materials All of these Quantity of the materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of steel work which is measured in sq.m, is Collapsible gates Rolling shutters All listed here Ventilators and glazing Collapsible gates Rolling shutters All listed here Ventilators and glazing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters Root slabs Floors Wall panels All of these Root slabs Floors Wall panels All of these ANSWER DOWNLOAD EXAMIANS APP