Estimating and Costing The volume is measured correct to the nearest 0.04 cum 0.02 cum 0.03 cum 0.01 cum 0.04 cum 0.02 cum 0.03 cum 0.01 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 2.5 sq m 6.0 sq m 8.0 sq m 4.0 sq m 2.5 sq m 6.0 sq m 8.0 sq m 4.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Excavation in trenches for foundation All of these Earth work in excavation Rock cutting Excavation in trenches for foundation All of these Earth work in excavation Rock cutting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 5.0 m³ 1.5 m³ 3.5 m³ 2.5 m³ 5.0 m³ 1.5 m³ 3.5 m³ 2.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The correct Prismoidal formula for volume is D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. All listed here Site clearance Steps in deep excavation Setting out of works All listed here Site clearance Steps in deep excavation Setting out of works ANSWER DOWNLOAD EXAMIANS APP