Estimating and Costing The expected out turn of half brick partition wall per mason per day is 4.0 m2 1.5 m2 2.0 m2 5.0 m2 4.0 m2 1.5 m2 2.0 m2 5.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item whose weight is added to the weight of respective item, is Cleats Brackets All listed here Bolts Cleats Brackets All listed here Bolts ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.90 m³ 1.00 m³ 0.98 m³ 0.94 m³ 0.90 m³ 1.00 m³ 0.98 m³ 0.94 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,500 m³ 26,000 m³ 26,500 m³ 27,000 m³ 27,500 m³ 26,000 m³ 26,500 m³ 27,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 15) chains (6 + 18) chains None of these (6 + 12) chains (6 + 15) chains (6 + 18) chains None of these (6 + 12) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: All listed here Length of short walls in-to-in is 3.20 m Length of long wall out-to-out is 6.80 m The total length of centre line of four walls is 20 m All listed here Length of short walls in-to-in is 3.20 m Length of long wall out-to-out is 6.80 m The total length of centre line of four walls is 20 m ANSWER DOWNLOAD EXAMIANS APP