Estimating and Costing The expected out turn of half brick partition wall per mason per day is 4.0 m2 5.0 m2 1.5 m2 2.0 m2 4.0 m2 5.0 m2 1.5 m2 2.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is 20 cm None of these 10 cm 15 cm 20 cm None of these 10 cm 15 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building The centre line is worked out separately for different sections of walls of a building All of these Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line length is reduced by half the layer of main wall joining the partition wall The centre line is worked out separately for different sections of walls of a building All of these Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line length is reduced by half the layer of main wall joining the partition wall ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Referring of given figure, pick up the correct statement from the following: Length of short walls in-to-in is 3.20 m All listed here The total length of centre line of four walls is 20 m Length of long wall out-to-out is 6.80 m Length of short walls in-to-in is 3.20 m All listed here The total length of centre line of four walls is 20 m Length of long wall out-to-out is 6.80 m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 1.5 m³ 5.0 m³ 2.5 m³ 3.5 m³ 1.5 m³ 5.0 m³ 2.5 m³ 3.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.04 cum 0.01 cum 0.03 cum 0.02 cum 0.04 cum 0.01 cum 0.03 cum 0.02 cum ANSWER DOWNLOAD EXAMIANS APP