Estimating and Costing The expected out turn of half brick partition wall per mason per day is 2.0 m2 1.5 m2 4.0 m2 5.0 m2 2.0 m2 1.5 m2 4.0 m2 5.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 150 mm 175 mm 200 mm 100 mm 150 mm 175 mm 200 mm 100 mm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. Cutting through walls and floors are included with the item All of these Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item All of these Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.50 m³ 1.00 m³ 1.75 m³ 1.25 m³ 1.50 m³ 1.00 m³ 1.75 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of All of these Bath room and lavatory Kitchen and pantry The walls along with doors and other openings All of these Bath room and lavatory Kitchen and pantry The walls along with doors and other openings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections All of these The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections All of these The area of mid-sections is calculated by using mean depth ANSWER DOWNLOAD EXAMIANS APP