Estimating and Costing The main factor to be considered while preparing a detailed estimate, is Availability of materials All of these Transportation of materials Quantity of the materials Availability of materials All of these Transportation of materials Quantity of the materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Brick walls are measured in sq. m if the thickness of the wall is 20 cm None of these 10 cm 15 cm 20 cm None of these 10 cm 15 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The detention period in a septic tank is assumed 40 minutes 25 minutes 30 minutes 20 minutes 40 minutes 25 minutes 30 minutes 20 minutes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are All of these Partly in excavation and partly in embankment Fully in excavation Fully in embankment All of these Partly in excavation and partly in embankment Fully in excavation Fully in embankment ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.247 m³ 0.295 m³ 0.200 m³ 0.274 m³ 0.247 m³ 0.295 m³ 0.200 m³ 0.274 m³ ANSWER DOWNLOAD EXAMIANS APP