Estimating and Costing The main factor to be considered while preparing a detailed estimate, is All of these Transportation of materials Availability of materials Quantity of the materials All of these Transportation of materials Availability of materials Quantity of the materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.04 cum 0.01 cum 0.02 cum 0.03 cum 0.04 cum 0.01 cum 0.02 cum 0.03 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.94 m³ 1.00 m³ 0.98 m³ 0.90 m³ 0.94 m³ 1.00 m³ 0.98 m³ 0.90 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Meter for length Square meters for volume Cubic metre for area Liter for capacity Meter for length Square meters for volume Cubic metre for area Liter for capacity ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 14° 8° 12° 10° 14° 8° 12° 10° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The unit of measurement is per quintal for the following: Rolling shutters Collapsible gates with rails Expanded metal wire netting M.S. reinforcement of R.C.C. works Rolling shutters Collapsible gates with rails Expanded metal wire netting M.S. reinforcement of R.C.C. works ANSWER DOWNLOAD EXAMIANS APP