Estimating and Costing The main factor to be considered while preparing a detailed estimate, is All of these Transportation of materials Availability of materials Quantity of the materials All of these Transportation of materials Availability of materials Quantity of the materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.25 kg 0.75 kg 0.50 kg 1.00 kg 0.25 kg 0.75 kg 0.50 kg 1.00 kg ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Anti-siphonage pipe is connected to Side of water closet Bottom of P trap W.C. Top of P trap W.C. Main soil pipe Side of water closet Bottom of P trap W.C. Top of P trap W.C. Main soil pipe ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Volume should be measured correct to 0.01 cum Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m All of these Volume should be measured correct to 0.01 cum Area should be measured correct to 0.01 sqm Dimension should be measured correct to 0.01 m All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.50 m³ 1.75 m³ 1.25 m³ 1.00 m³ 1.50 m³ 1.75 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The assumption on which the trapezoidal formula for volumes is based, is The mid-area of a pyramid is half the average area of the ends The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied The end sections are parallel planes All listed here The mid-area of a pyramid is half the average area of the ends The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied The end sections are parallel planes All listed here ANSWER DOWNLOAD EXAMIANS APP