Estimating and Costing The main factor to be considered while preparing a detailed estimate, is Availability of materials Transportation of materials All of these Quantity of the materials Availability of materials Transportation of materials All of these Quantity of the materials ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. All of these Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item All of these Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.025 0.04 0.02 0.05 0.025 0.04 0.02 0.05 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Steps in deep excavation Setting out of works Site clearance All listed here Steps in deep excavation Setting out of works Site clearance All listed here ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes All of these Connection to drains Setting and laying Bed concreting All of these Connection to drains Setting and laying Bed concreting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ 1.50 m³ 1.25 m³ 1.75 m³ 1.00 m³ ANSWER DOWNLOAD EXAMIANS APP