Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 4.0 sq m 2.5 sq m 8.0 sq m 6.0 sq m 4.0 sq m 2.5 sq m 8.0 sq m 6.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,000 m³ 27,500 m³ 26,000 m³ 26,500 m³ 27,000 m³ 27,500 m³ 26,000 m³ 26,500 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The inspection pit or chamber is a manhole provided in a base drainage system At every change of direction At every change of gradient At every 30 m intervals All of these At every change of direction At every change of gradient At every 30 m intervals All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The order of booking dimensions is Length, breadth, height None of these Breadth, length, height Height, breadth, length Length, breadth, height None of these Breadth, length, height Height, breadth, length ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The weight of an item is measured correct to nearest 0.25 kg 1.00 kg 0.75 kg 0.50 kg 0.25 kg 1.00 kg 0.75 kg 0.50 kg ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The unit of measurement is per quintal for the following: M.S. reinforcement of R.C.C. works Expanded metal wire netting Rolling shutters Collapsible gates with rails M.S. reinforcement of R.C.C. works Expanded metal wire netting Rolling shutters Collapsible gates with rails ANSWER DOWNLOAD EXAMIANS APP