Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 8.0 sq m 2.5 sq m 4.0 sq m 6.0 sq m 8.0 sq m 2.5 sq m 4.0 sq m 6.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Size, capacity and materials need be specified for All of these Stop-cocks Ball valves Bib-cocks All of these Stop-cocks Ball valves Bib-cocks ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Excavation in trenches for foundation Rock cutting Earth work in excavation All of these Excavation in trenches for foundation Rock cutting Earth work in excavation All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is None of these (6 + 15) chains (6 + 12) chains (6 + 18) chains None of these (6 + 15) chains (6 + 12) chains (6 + 18) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is d × d × s √[d² × (ds)²] L.D √(1 + s²) 2 L.D √(1 + s²) d × d × s √[d² × (ds)²] L.D √(1 + s²) 2 L.D √(1 + s²) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Circular buildings Octagonal buildings All of these Hexagonal buildings Circular buildings Octagonal buildings All of these Hexagonal buildings ANSWER DOWNLOAD EXAMIANS APP