Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 6.0 sq m 8.0 sq m 2.5 sq m 4.0 sq m 6.0 sq m 8.0 sq m 2.5 sq m 4.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing According to ISI method of measurement, the order of the sequence is Breadth, length, height Length, breadth, height Height, length, breadth None of these Breadth, length, height Length, breadth, height Height, length, breadth None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is not made in square meters in case of R.C. Chhajja Form works Concrete Jeffries P.C. (Damp proof course) R.C. Chhajja Form works Concrete Jeffries P.C. (Damp proof course) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is 2 L.D √(1 + s²) L.D √(1 + s²) d × d × s √[d² × (ds)²] 2 L.D √(1 + s²) L.D √(1 + s²) d × d × s √[d² × (ds)²] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of steel work which is measured in sq.m, is Collapsible gates Rolling shutters All listed here Ventilators and glazing Collapsible gates Rolling shutters All listed here Ventilators and glazing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The damp proof course (D.P.C.) is measured in Sq. m Meters None of these Cub. m Sq. m Meters None of these Cub. m ANSWER DOWNLOAD EXAMIANS APP