Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 8.0 sq m 6.0 sq m 4.0 sq m 2.5 sq m 8.0 sq m 6.0 sq m 4.0 sq m 2.5 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of All of these Earth work in excavation Excavation in trenches for foundation Rock cutting All of these Earth work in excavation Excavation in trenches for foundation Rock cutting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 59 D 39 D 30 D 50 D 59 D 39 D 30 D 50 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is measured in sq metre, in case of Half brick walls or the partition Honey comb brick work All of these Brick flat soling Half brick walls or the partition Honey comb brick work All of these Brick flat soling ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is not measured in cu m in case of One or more than one brick wall Brick work in arches Reinforced brick work Half brick wall One or more than one brick wall Brick work in arches Reinforced brick work Half brick wall ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3225 m³ 3300 m³ 3250 m³ 3275 m³ 3225 m³ 3300 m³ 3250 m³ ANSWER DOWNLOAD EXAMIANS APP