Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 4.0 sq m 6.0 sq m 2.5 sq m 8.0 sq m 4.0 sq m 6.0 sq m 2.5 sq m 8.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.02 cum 0.03 cum 0.01 cum 0.04 cum 0.02 cum 0.03 cum 0.01 cum 0.04 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Hexagonal buildings Circular buildings All of these Octagonal buildings Hexagonal buildings Circular buildings All of these Octagonal buildings ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.00 m³ 1.75 m³ 1.50 m³ 1.25 m³ 1.00 m³ 1.75 m³ 1.50 m³ 1.25 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the incorrect statement regarding a master trap from the following: It is provided in between the lower end of the house drain and the street sewer The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe The water seal is less than that of ordinary traps It is provided a cleaning eye at the top of the trap It is provided in between the lower end of the house drain and the street sewer The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe The water seal is less than that of ordinary traps It is provided a cleaning eye at the top of the trap ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made for stone work in square metre in case of Wall facing Building work Columns, lintels, copings (A) and (B) of the above Wall facing Building work Columns, lintels, copings (A) and (B) of the above ANSWER DOWNLOAD EXAMIANS APP