Estimating and Costing In the mid-section formula The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The area of mid-sections is calculated by using mean depth All of these The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The area of mid-sections is calculated by using mean depth All of these The mean depth is the average of depths of two consecutive sections ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as Surface dressing Excavation Cutting Surface excavation Surface dressing Excavation Cutting Surface excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is measured in sq metre, in case of Honey comb brick work Half brick walls or the partition Brick flat soling All of these Honey comb brick work Half brick walls or the partition Brick flat soling All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Circular buildings Octagonal buildings Hexagonal buildings All of these Circular buildings Octagonal buildings Hexagonal buildings All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Connection to drains Setting and laying Bed concreting All of these Connection to drains Setting and laying Bed concreting All of these ANSWER DOWNLOAD EXAMIANS APP