Estimating and Costing The measurement is made for stone work in square metre in case of Columns, lintels, copings (A) and (B) of the above Wall facing Building work Columns, lintels, copings (A) and (B) of the above Wall facing Building work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of steel work which is measured in sq.m, is All listed here Rolling shutters Collapsible gates Ventilators and glazing All listed here Rolling shutters Collapsible gates Ventilators and glazing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. Setting out of works Site clearance All listed here Steps in deep excavation Setting out of works Site clearance All listed here Steps in deep excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.02 cum 0.03 cum 0.01 cum 0.04 cum 0.02 cum 0.03 cum 0.01 cum 0.04 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3225 m³ 3250 m³ 3300 m³ 3275 m³ 3225 m³ 3250 m³ 3300 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 1.00 m³ 0.94 m³ 0.90 m³ 0.98 m³ 1.00 m³ 0.94 m³ 0.90 m³ 0.98 m³ ANSWER DOWNLOAD EXAMIANS APP