Estimating and Costing Pick up the correct statement in case of water supply. Cutting through walls and floors are included with the item All of these Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item All of these Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is measured in sq metre, in case of Brick flat soling All of these Honey comb brick work Half brick walls or the partition Brick flat soling All of these Honey comb brick work Half brick walls or the partition ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.274 m³ 0.247 m³ 0.200 m³ 0.295 m³ 0.274 m³ 0.247 m³ 0.200 m³ 0.295 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are All of these Partly in excavation and partly in embankment Fully in embankment Fully in excavation All of these Partly in excavation and partly in embankment Fully in embankment Fully in excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 175 mm 200 mm 150 mm 100 mm 175 mm 200 mm 150 mm 100 mm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 75 cm to 80 cm 60 cm 80 cm 70 cm 75 cm to 80 cm 60 cm 80 cm 70 cm ANSWER DOWNLOAD EXAMIANS APP