Estimating and Costing The detention period in a septic tank is assumed 40 minutes 20 minutes 30 minutes 25 minutes 40 minutes 20 minutes 30 minutes 25 minutes ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. Cutting through walls and floors are included with the item Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately All of these Cutting through walls and floors are included with the item Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of The walls along with doors and other openings All of these Bath room and lavatory Kitchen and pantry The walls along with doors and other openings All of these Bath room and lavatory Kitchen and pantry ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 100 mm 200 mm 175 mm 150 mm 100 mm 200 mm 175 mm 150 mm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Bed concreting Connection to drains All of these Setting and laying Bed concreting Connection to drains All of these Setting and laying ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 3.00 cum 2.00 cum 4.00 cum 1.00 cum 3.00 cum 2.00 cum 4.00 cum 1.00 cum ANSWER DOWNLOAD EXAMIANS APP