Estimating and Costing If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by Mid-section formula All of these Trapezoidal formula Prismoidal formula Mid-section formula All of these Trapezoidal formula Prismoidal formula ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The correct Prismoidal formula for volume is D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas] D [first area + last area + Ʃ Even area + 2 Ʃ odd areas] D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas] D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas] ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. All listed here Site clearance Steps in deep excavation Setting out of works All listed here Site clearance Steps in deep excavation Setting out of works ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3225 m³ 3250 m³ 3300 m³ 3275 m³ 3225 m³ 3250 m³ 3300 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are Brickwork Flooring, Wood work, Steel work All of these Brickwork, Stone work, Roofing Earthwork, Concrete work, Brick work Brickwork Flooring, Wood work, Steel work All of these Brickwork, Stone work, Roofing Earthwork, Concrete work, Brick work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall All of these Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item The centre line is worked out separately for different sections of walls of a building The centre line length is reduced by half the layer of main wall joining the partition wall All of these ANSWER DOWNLOAD EXAMIANS APP