Estimating and Costing If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by All of these Mid-section formula Trapezoidal formula Prismoidal formula All of these Mid-section formula Trapezoidal formula Prismoidal formula ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. Pipes are classified according to their sizes and quality All of these Cutting through walls and floors are included with the item Pipes laid in trenches and pipes fixed to walls are measured separately Pipes are classified according to their sizes and quality All of these Cutting through walls and floors are included with the item Pipes laid in trenches and pipes fixed to walls are measured separately ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.247 m³ 0.274 m³ 0.200 m³ 0.295 m³ 0.247 m³ 0.274 m³ 0.200 m³ 0.295 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections All of these The area of mid-sections is calculated by using mean depth The mean depth is the average of depths of two consecutive sections ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While estimating the qualities for the construction of a building, the correct metric unit is Liter for capacity Cubic metre for area Square meters for volume Meter for length Liter for capacity Cubic metre for area Square meters for volume Meter for length ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.02 cum 0.04 cum 0.01 cum 0.03 cum 0.02 cum 0.04 cum 0.01 cum 0.03 cum ANSWER DOWNLOAD EXAMIANS APP