Estimating and Costing If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by All of these Trapezoidal formula Mid-section formula Prismoidal formula All of these Trapezoidal formula Mid-section formula Prismoidal formula ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The unit of measurement is per quintal for the following: M.S. reinforcement of R.C.C. works Collapsible gates with rails Expanded metal wire netting Rolling shutters M.S. reinforcement of R.C.C. works Collapsible gates with rails Expanded metal wire netting Rolling shutters ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The damp proof course (D.P.C.) is measured in Meters Sq. m Cub. m None of these Meters Sq. m Cub. m None of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.50 m³ 1.25 m³ 1.00 m³ 1.75 m³ 1.50 m³ 1.25 m³ 1.00 m³ 1.75 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. All listed here Steps in deep excavation Setting out of works Site clearance All listed here Steps in deep excavation Setting out of works Site clearance ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made in square metre in case of Cement concrete in foundation R.C.C. structure Hollow concrete block wall None of these Cement concrete in foundation R.C.C. structure Hollow concrete block wall None of these ANSWER DOWNLOAD EXAMIANS APP