Estimating and Costing The height of the sink of wash basin above floor level is kept 75 cm to 80 cm 60 cm 70 cm 80 cm 75 cm to 80 cm 60 cm 70 cm 80 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of All of these The walls along with doors and other openings Kitchen and pantry Bath room and lavatory All of these The walls along with doors and other openings Kitchen and pantry Bath room and lavatory ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3300 m³ 3275 m³ 3250 m³ 3225 m³ 3300 m³ 3275 m³ 3250 m³ 3225 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is 0.94 m³ 1.00 m³ 0.90 m³ 0.98 m³ 0.94 m³ 1.00 m³ 0.90 m³ 0.98 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 3.5 m³ 1.5 m³ 5.0 m³ 2.5 m³ 3.5 m³ 1.5 m³ 5.0 m³ 2.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The measurement is made in square metre in case of None of these R.C.C. structure Hollow concrete block wall Cement concrete in foundation None of these R.C.C. structure Hollow concrete block wall Cement concrete in foundation ANSWER DOWNLOAD EXAMIANS APP