Estimating and Costing The height of the sink of wash basin above floor level is kept 75 cm to 80 cm 60 cm 80 cm 70 cm 75 cm to 80 cm 60 cm 80 cm 70 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,000 m³ 26,500 m³ 27,500 m³ 26,000 m³ 27,000 m³ 26,500 m³ 27,500 m³ 26,000 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item whose weight is added to the weight of respective item, is Bolts All listed here Cleats Brackets Bolts All listed here Cleats Brackets ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The item of steel work which is measured in sq.m, is Ventilators and glazing Collapsible gates All listed here Rolling shutters Ventilators and glazing Collapsible gates All listed here Rolling shutters ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is not measured in cu m in case of Half brick wall Brick work in arches One or more than one brick wall Reinforced brick work Half brick wall Brick work in arches One or more than one brick wall Reinforced brick work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The area is measured correct to the nearest 0.03 sqm 0.01 sqm 0.04 sqm 0.02 sqm 0.03 sqm 0.01 sqm 0.04 sqm 0.02 sqm ANSWER DOWNLOAD EXAMIANS APP