Estimating and Costing The height of the sink of wash basin above floor level is kept 70 cm 80 cm 60 cm 75 cm to 80 cm 70 cm 80 cm 60 cm 75 cm to 80 cm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is not measured in cu m in case of One or more than one brick wall Reinforced brick work Half brick wall Brick work in arches One or more than one brick wall Reinforced brick work Half brick wall Brick work in arches ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 6.0 sq m 2.5 sq m 8.0 sq m 4.0 sq m 6.0 sq m 2.5 sq m 8.0 sq m 4.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 3.00 cum 2.00 cum 1.00 cum 4.00 cum 3.00 cum 2.00 cum 1.00 cum 4.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,000 m³ 27,000 m³ 27,500 m³ 26,500 m³ 26,000 m³ 27,000 m³ 27,500 m³ 26,500 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The mean depth is the average of depths of two consecutive sections All of these The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections All of these The area of mid-sections is calculated by using mean depth The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections ANSWER DOWNLOAD EXAMIANS APP