Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of All of these Excavation in trenches for foundation Earth work in excavation Rock cutting All of these Excavation in trenches for foundation Earth work in excavation Rock cutting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The concrete work for the following part of the building of specified thickness is measured in square meters Root slabs Wall panels Floors All of these Root slabs Wall panels Floors All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The unit of measurement is per quintal for the following: Collapsible gates with rails Expanded metal wire netting Rolling shutters M.S. reinforcement of R.C.C. works Collapsible gates with rails Expanded metal wire netting Rolling shutters M.S. reinforcement of R.C.C. works ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The 'centre line method' is specially adopted for estimating Hexagonal buildings Octagonal buildings Circular buildings All of these Hexagonal buildings Octagonal buildings Circular buildings All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The plinth area of a building not includes Area of cantilevered porch Area of the walls at the floor level Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing Area of cantilevered porch Area of the walls at the floor level Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3250 m³ 3300 m³ 3275 m³ 3225 m³ 3250 m³ 3300 m³ 3275 m³ 3225 m³ ANSWER DOWNLOAD EXAMIANS APP