Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Rock cutting Earth work in excavation All of these Excavation in trenches for foundation Rock cutting Earth work in excavation All of these Excavation in trenches for foundation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3225 m³ 3300 m³ 3250 m³ 3275 m³ 3225 m³ 3300 m³ 3250 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the item whose weight is added to the weight of respective item, is Brackets All listed here Bolts Cleats Brackets All listed here Bolts Cleats ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.295 m³ 0.274 m³ 0.247 m³ 0.200 m³ 0.295 m³ 0.274 m³ 0.247 m³ 0.200 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 12 mm plastering with cement mortar is 2.5 sq m 6.0 sq m 4.0 sq m 8.0 sq m 2.5 sq m 6.0 sq m 4.0 sq m 8.0 sq m ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. All listed here Site clearance Steps in deep excavation Setting out of works All listed here Site clearance Steps in deep excavation Setting out of works ANSWER DOWNLOAD EXAMIANS APP