Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of All of these Excavation in trenches for foundation Rock cutting Earth work in excavation All of these Excavation in trenches for foundation Rock cutting Earth work in excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If tensile stress of a steel rod of diameter ‘D’ is 1400 kg/cm² and bond stress is 6 kg/cm², the required bond length of the rod is 50 D 59 D 39 D 30 D 50 D 59 D 39 D 30 D ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is not measured in cu m in case of One or more than one brick wall Brick work in arches Half brick wall Reinforced brick work One or more than one brick wall Brick work in arches Half brick wall Reinforced brick work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is None of these (6 + 15) chains (6 + 18) chains (6 + 12) chains None of these (6 + 15) chains (6 + 18) chains (6 + 12) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of Kitchen and pantry Bath room and lavatory The walls along with doors and other openings All of these Kitchen and pantry Bath room and lavatory The walls along with doors and other openings All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The following item of earth work is not measured separately. All listed here Setting out of works Site clearance Steps in deep excavation All listed here Setting out of works Site clearance Steps in deep excavation ANSWER DOWNLOAD EXAMIANS APP