Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Earth work in excavation Rock cutting All of these Excavation in trenches for foundation Earth work in excavation Rock cutting All of these Excavation in trenches for foundation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.247 m³ 0.200 m³ 0.295 m³ 0.274 m³ 0.247 m³ 0.200 m³ 0.295 m³ 0.274 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The brick work is not measured in cu m in case of One or more than one brick wall Brick work in arches Half brick wall Reinforced brick work One or more than one brick wall Brick work in arches Half brick wall Reinforced brick work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,000 m³ 26,000 m³ 26,500 m³ 27,500 m³ 27,000 m³ 26,000 m³ 26,500 m³ 27,500 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 2.5 m³ 3.5 m³ 5.0 m³ 1.5 m³ 2.5 m³ 3.5 m³ 5.0 m³ 1.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is (6 + 12) chains (6 + 15) chains (6 + 18) chains None of these (6 + 12) chains (6 + 15) chains (6 + 18) chains None of these ANSWER DOWNLOAD EXAMIANS APP