Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Rock cutting Excavation in trenches for foundation All of these Earth work in excavation Rock cutting Excavation in trenches for foundation All of these Earth work in excavation ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the incorrect statement regarding a master trap from the following: The water seal is less than that of ordinary traps It is provided in between the lower end of the house drain and the street sewer It is provided a cleaning eye at the top of the trap The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe The water seal is less than that of ordinary traps It is provided in between the lower end of the house drain and the street sewer It is provided a cleaning eye at the top of the trap The mica flap valve which opens inwards only, is fitted at the top of the inlet pipe ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 1.00 cum 2.00 cum 4.00 cum 3.00 cum 1.00 cum 2.00 cum 4.00 cum 3.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The plinth area of a building not includes Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing Area of cantilevered porch Area of the walls at the floor level Internal shaft for sanitary installations up to 2 sq m. in area Lift and wall including landing Area of cantilevered porch Area of the walls at the floor level ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In case of laying gullies, siphons, intercepting traps, the cost includes Setting and laying Bed concreting Connection to drains All of these Setting and laying Bed concreting Connection to drains All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth All of these ANSWER DOWNLOAD EXAMIANS APP