Estimating and Costing The rate of payment is made for 100 cu m (per % cu m) in case of Excavation in trenches for foundation Earth work in excavation All of these Rock cutting Excavation in trenches for foundation Earth work in excavation All of these Rock cutting ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 26,000 m³ 27,500 m³ 27,000 m³ 26,500 m³ 26,000 m³ 27,500 m³ 27,000 m³ 26,500 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The volume is measured correct to the nearest 0.01 cum 0.02 cum 0.04 cum 0.03 cum 0.01 cum 0.02 cum 0.04 cum 0.03 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The most reliable estimate is Preliminary estimate Plinth area estimate Detailed estimate Cube rate estimate Preliminary estimate Plinth area estimate Detailed estimate Cube rate estimate ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 2.5 m³ 3.5 m³ 5.0 m³ 1.5 m³ 2.5 m³ 3.5 m³ 5.0 m³ 1.5 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The height of the sink of wash basin above floor level is kept 75 cm to 80 cm 70 cm 80 cm 60 cm 75 cm to 80 cm 70 cm 80 cm 60 cm ANSWER DOWNLOAD EXAMIANS APP