Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building The centre line length is reduced by half the layer of main wall joining the partition wall The centre line is worked out separately for different sections of walls of a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these The centre line length is reduced by half the layer of main wall joining the partition wall The centre line is worked out separately for different sections of walls of a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3300 m³ 3250 m³ 3275 m³ 3225 m³ 3300 m³ 3250 m³ 3275 m³ 3225 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 4.00 cum 2.00 cum 3.00 cum 1.00 cum 4.00 cum 2.00 cum 3.00 cum 1.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of half brick partition wall per mason per day is 1.5 m2 2.0 m2 4.0 m2 5.0 m2 1.5 m2 2.0 m2 4.0 m2 5.0 m2 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of 2.5 cm cement concrete floor per mansion per day 2.5 sqm 7.5 sqm 10 sqm 5.0 sqm 2.5 sqm 7.5 sqm 10 sqm 5.0 sqm ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Berms are provided in canals if these are All of these Fully in embankment Partly in excavation and partly in embankment Fully in excavation All of these Fully in embankment Partly in excavation and partly in embankment Fully in excavation ANSWER DOWNLOAD EXAMIANS APP