Estimating and Costing Pick up the correct statement regarding the centre line method of estimating a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these The centre line length is reduced by half the layer of main wall joining the partition wall The centre line is worked out separately for different sections of walls of a building Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item All of these The centre line length is reduced by half the layer of main wall joining the partition wall The centre line is worked out separately for different sections of walls of a building ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing While preparing a detailed estimate Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm All of these Volume should be measured correct to 0.01 cum Dimension should be measured correct to 0.01 m Area should be measured correct to 0.01 sqm All of these ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the excavation where measurements are made in square meters for payment. Both (B) and (C) Ordinary cuttings up to 1 m Surface excavation up to 30 cm depths Surface dressing up to 15 cm depths Both (B) and (C) Ordinary cuttings up to 1 m Surface excavation up to 30 cm depths Surface dressing up to 15 cm depths ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is 1.75 m³ 1.00 m³ 1.25 m³ 1.50 m³ 1.75 m³ 1.00 m³ 1.25 m³ 1.50 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For the construction of buildings, the subheads of the estimate are All of these Brickwork, Stone work, Roofing Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work All of these Brickwork, Stone work, Roofing Brickwork Flooring, Wood work, Steel work Earthwork, Concrete work, Brick work ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ANSWER DOWNLOAD EXAMIANS APP