Estimating and Costing The slope of the outlet of 'P trap' below the horizontal is kept 12° 8° 14° 10° 12° 8° 14° 10° ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Carpet area does not include the area of All of these Bath room and lavatory The walls along with doors and other openings Kitchen and pantry All of these Bath room and lavatory The walls along with doors and other openings Kitchen and pantry ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is 3275 m³ 3225 m³ 3250 m³ 3300 m³ 3275 m³ 3225 m³ 3250 m³ 3300 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The expected out turn for earth work in excavation in ordinary soil per workman per day is 1.00 cum 4.00 cum 3.00 cum 2.00 cum 1.00 cum 4.00 cum 3.00 cum 2.00 cum ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The floor area includes the area of the balcony up to 1 0.75 0.25 0.5 1 0.75 0.25 0.5 ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by Trapezoidal formula Mid-section formula All of these Prismoidal formula Trapezoidal formula Mid-section formula All of these Prismoidal formula ANSWER DOWNLOAD EXAMIANS APP