Estimating and Costing The measurement is made in square metre in case of R.C.C. structure Cement concrete in foundation None of these Hollow concrete block wall R.C.C. structure Cement concrete in foundation None of these Hollow concrete block wall ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing Pick up the correct statement in case of water supply. Pipes are classified according to their sizes and quality All of these Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item Pipes are classified according to their sizes and quality All of these Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is None of these (6 + 18) chains (6 + 15) chains (6 + 12) chains None of these (6 + 18) chains (6 + 15) chains (6 + 12) chains ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r - s) ½ × (b + rd)²/(r - s) ⅓ × (b - rd)²/(r + s) ⅓ × (b - rd)²/(s - r) ⅓ × (b - rd)²/(r - s) ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is 0.274 m³ 0.200 m³ 0.247 m³ 0.295 m³ 0.274 m³ 0.200 m³ 0.247 m³ 0.295 m³ ANSWER DOWNLOAD EXAMIANS APP
Estimating and Costing In the mid-section formula The area of mid-sections is calculated by using mean depth All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections ANSWER DOWNLOAD EXAMIANS APP