The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is

3275 m³
3225 m³
3250 m³
3300 m³

ANSWER DOWNLOAD EXAMIANS APP

Estimating and Costing
The assumption on which the trapezoidal formula for volumes is based, is

The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied
The mid-area of a pyramid is half the average area of the ends
The end sections are parallel planes
All listed here