Power Systems A 100 MVA alternator operating at full load at 50 Hz. H = 4 MWsec/MVA, Td = 0.5 sec. One of the transmission line is tripped. So that output of generator is reduced to 70 MW. Find the frequency deviation during this time? -0.56 -0.92 0.92 0.56 -0.56 -0.92 0.92 0.56 ANSWER DOWNLOAD EXAMIANS APP
Power Systems In which of the following frequency control method tie line may be overloaded? All of these parallel frequency flat tie line control flat frequency control All of these parallel frequency flat tie line control flat frequency control ANSWER DOWNLOAD EXAMIANS APP
Power Systems The equation of area control error(ACE) is ACE = ΔPtie - 1/b.Δf ACE = ΔPtie - b.Δf ACE = ΔPtie +1/ b.Δf ACE = ΔPtie + b.Δf ACE = ΔPtie - 1/b.Δf ACE = ΔPtie - b.Δf ACE = ΔPtie +1/ b.Δf ACE = ΔPtie + b.Δf ANSWER DOWNLOAD EXAMIANS APP
Power Systems Power system network has a total power of 5000 MW at 50 Hz supplying to the different consumers. Frequency is varying at 1.5% per change of 2% load. Assume R =0.004 Hz/MW. Find the steady state frequency deviation if a sudden loss of 200 MW occur due to tripping of one of the transmission line? 50 Hz -0.52 Hz 0.48 Hz 0.52 Hz 50 Hz -0.52 Hz 0.48 Hz 0.52 Hz ANSWER DOWNLOAD EXAMIANS APP
Power Systems Units of incremental cost is Rs/hr RsMW/hr MWhr/Rs Rs/MWhr Rs/hr RsMW/hr MWhr/Rs Rs/MWhr ANSWER DOWNLOAD EXAMIANS APP