Power Systems
Which of the following plants is/are base load plants

 pump storage
 run off river
 both 1 and 2
 nuclear

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW for remaining 12 hours. The plant capacity factor for the station is

 0.75
 0.6
 0.5
 1

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW for remaining 12 hours. If the load factor is 0.8. Find the reserve capacity of the station?

 5 MW
 9 MW
 18 MW
 10 MW

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
A power station has a maximum demand of 15000 kW. The annual load factor is 50% and plant capacity factor is 40%. What is the reserve capacity of the plant?

 6000 kW
 7500 kW
 3750 kW
 3000 kW

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The daily energy produced in thermal power station is 720 MWh at a load factor of 0.6. What is the maximum demand of the station?

 720 MW
 72 MW
 30 MW
 50 MW

ANSWER DOWNLOAD EXAMIANS APP
  • «
  • 1
  • ...
  • 41
  • 42
  • 43
  • 44
  • 45
  • ...
  • 126
  • »

GO TO PAGE

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑