Power Systems Which of the following plants is/are base load plants run off river pump storage nuclear both 1 and 2 run off river pump storage nuclear both 1 and 2 ANSWER DOWNLOAD EXAMIANS APP
Power Systems A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW for remaining 12 hours. The plant capacity factor for the station is 0.6 0.5 0.75 1 0.6 0.5 0.75 1 ANSWER DOWNLOAD EXAMIANS APP
Power Systems A thermal generating station has an installed capacity of 15 MW and supplies a daily load of 10 MW for 12 hours and 5 MW for remaining 12 hours. If the load factor is 0.8. Find the reserve capacity of the station? 9 MW 10 MW 18 MW 5 MW 9 MW 10 MW 18 MW 5 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems A power station has a maximum demand of 15000 kW. The annual load factor is 50% and plant capacity factor is 40%. What is the reserve capacity of the plant? 3750 kW 3000 kW 7500 kW 6000 kW 3750 kW 3000 kW 7500 kW 6000 kW ANSWER DOWNLOAD EXAMIANS APP
Power Systems The daily energy produced in thermal power station is 720 MWh at a load factor of 0.6. What is the maximum demand of the station? 720 MW 50 MW 72 MW 30 MW 720 MW 50 MW 72 MW 30 MW ANSWER DOWNLOAD EXAMIANS APP