Industrial Engineering and Production Management The time which results in the least possible direct cost of an activity is known as Crash time Slow time Normal time Standard time Crash time Slow time Normal time Standard time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative The activity is critical and any delay in its performance will delay the completion of whole project It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time All of these The activity is critical and any delay in its performance will delay the completion of whole project It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is positive The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If TL is the largest allowable event occurrence time, total activity slack (s) is equal to All of these Latest start time earliest start time Latest finish time earliest finish time (EFT) TLEFT All of these Latest start time earliest start time Latest finish time earliest finish time (EFT) TLEFT ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Tick the odd man out Galileo Drucker McGregor Taylor Galileo Drucker McGregor Taylor ANSWER DOWNLOAD EXAMIANS APP