Industrial Engineering and Production Management When slack of an activity is negative It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project All of these It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management String diagram is used For checking the relative values of various layouts When a group of workers are working at a place All of these Where processes require the operator to be moved from one place to another For checking the relative values of various layouts When a group of workers are working at a place All of these Where processes require the operator to be moved from one place to another ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management According to MAPI formula, the old machine should be replaced by new one when (Here, CAM = Challenger's Adverse minimum, DAM = Defender's Adverse minimum) CAM = DAM CAM < DAM CAM > DAM There is no such criterion CAM = DAM CAM < DAM CAM > DAM There is no such criterion ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The critical path of a network represents Maximum cost required for completion of project The maximum time required for completion of project Minimum cost required for completion of project The minimum time required for completion of project Maximum cost required for completion of project The maximum time required for completion of project Minimum cost required for completion of project The minimum time required for completion of project ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.66 0.5 0.84 0.95 0.66 0.5 0.84 0.95 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Halsey plan of wage incentive Does not guarantee minimum wage Is applied to all level of workers Is not applied to all level of workers Is based upon efficiency of worker Does not guarantee minimum wage Is applied to all level of workers Is not applied to all level of workers Is based upon efficiency of worker ANSWER DOWNLOAD EXAMIANS APP