When slack of an activity is negative

All of these
The activity is critical and any delay in its performance will delay the completion of whole project
It represents a situation where extra resources are available and the completion of project is not delayed
It represents that a programme falls behind schedule and additional resources are required to complete the project in time

ANSWER DOWNLOAD EXAMIANS APP