Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.95 0.84 0.66 0.5 0.95 0.84 0.66 0.5 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT/CPM, techniques can be used for following applications All of these Once through project Research and development Maintenance jobs All of these Once through project Research and development Maintenance jobs ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In a PERT chart Only important activities should be numbered Only selected activities are numbered All activities should be numbered Only critical activities are numbered Only important activities should be numbered Only selected activities are numbered All activities should be numbered Only critical activities are numbered ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following are the principles of material handling? All of these Keep all the handling to the minimum Select only efficient handling equipment Move the heaviest weight to the least distance All of these Keep all the handling to the minimum Select only efficient handling equipment Move the heaviest weight to the least distance ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Break-even analysis can be used for There is no such criterion Long run analysis Short run analysis Average of above two run analysis There is no such criterion Long run analysis Short run analysis Average of above two run analysis ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A milestone chart Points outgoing ahead of schedule of jobs, if any None of the these Depicts the delay of jobs, if any Shows the inter dependences of various jobs Points outgoing ahead of schedule of jobs, if any None of the these Depicts the delay of jobs, if any Shows the inter dependences of various jobs ANSWER DOWNLOAD EXAMIANS APP