Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.5 0.95 0.66 0.84 0.5 0.95 0.66 0.84 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management String diagram is used For checking the relative values of various layouts Where processes require the operator to be moved from one place to another When a group of workers are working at a place All of these For checking the relative values of various layouts Where processes require the operator to be moved from one place to another When a group of workers are working at a place All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT has following time estimate One time estimate Three time estimate Two time estimate Four time estimate One time estimate Three time estimate Two time estimate Four time estimate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Standard time as compared to normal time is There is no such correlation Greater Equal Smaller There is no such correlation Greater Equal Smaller ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Queuing theory is associated with Waiting time Production time Sales Inspection time Waiting time Production time Sales Inspection time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Routing assists engineers in deciding in advance The layout of factory facilities The methods of proper utilization of manpower The methods of proper utilization of machines The flow of material in the plant The layout of factory facilities The methods of proper utilization of manpower The methods of proper utilization of machines The flow of material in the plant ANSWER DOWNLOAD EXAMIANS APP