Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.66 0.5 0.95 0.84 0.66 0.5 0.95 0.84 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management According to MAPI formula, the old machine should be replaced by new one when (Here, CAM = Challenger's Adverse minimum, DAM = Defender's Adverse minimum) CAM = DAM There is no such criterion CAM < DAM CAM > DAM CAM = DAM There is no such criterion CAM < DAM CAM > DAM ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In inventory control, the economic order quantity is the Optimum lot size Highest level of inventory Capability of a plant to produce Lot corresponding to break-even point Optimum lot size Highest level of inventory Capability of a plant to produce Lot corresponding to break-even point ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The probability distribution of activity times in PERT follows following distribution Beta Normal Exponential Binomial Beta Normal Exponential Binomial ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The procedure of modifying work content to give more meaning and enjoyment to the job by involving employees in planning, organisation and control of their work, is termed as Job rotation Job evaluation Job enlargement Job enrichment Job rotation Job evaluation Job enlargement Job enrichment ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Military type of organisation is known as Line, staff and functional organisation Functional organisation Line and staff organisation Line organisation Line, staff and functional organisation Functional organisation Line and staff organisation Line organisation ANSWER DOWNLOAD EXAMIANS APP