Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.5 0.66 0.95 0.84 0.5 0.66 0.95 0.84 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The simplex method is the basic method for Operation research Linear programming Value analysis Model analysis Operation research Linear programming Value analysis Model analysis ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Tick the odd man out Taylor Galileo Drucker McGregor Taylor Galileo Drucker McGregor ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The break-even point represents The time when unit can run without any loss and profit The time when company can make maximum profits Time when industry will undergo loss The most economical level of operation of any industry The time when unit can run without any loss and profit The time when company can make maximum profits Time when industry will undergo loss The most economical level of operation of any industry ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The technique of value analysis can be applied to Simple items only Crash programmer items only Complicated items only Any item Simple items only Crash programmer items only Complicated items only Any item ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Dispatching Determines the programme for the operations Prescribes the sequence of operations to be followed Regulates the progress of job through various processes Is concerned with the starting of processes Determines the programme for the operations Prescribes the sequence of operations to be followed Regulates the progress of job through various processes Is concerned with the starting of processes ANSWER DOWNLOAD EXAMIANS APP