Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.84 0.5 0.95 0.66 0.84 0.5 0.95 0.66 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Basic motion time study gives times for basic motions in ten thousandths of Second Day Hour Minute Second Day Hour Minute ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The probability distribution of project completion in PERT follows following distribution Gaussian Normal Exponential Binomial Gaussian Normal Exponential Binomial ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode Late finish Early finish Late start Early start Late finish Early finish Late start Early start ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management One time measurement unit (TMU) in method time measurement system equals 0.001 minute 0.0001 minute 0.0006 minute 0.006 minute 0.001 minute 0.0001 minute 0.0006 minute 0.006 minute ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Emergency rush order can be pushed more effectively in Intermittent production Job production Continuous production Automatic production Intermittent production Job production Continuous production Automatic production ANSWER DOWNLOAD EXAMIANS APP