Industrial Engineering and Production Management The essential condition for the decompression of an activity is that The project time should change due to decompression After decompression the time of an activity invariably exceeds its normal time An activity could be decompressed to the maximum extent of its normal time An activity could be decompressed to the maximum extent of its normal time The project time should change due to decompression After decompression the time of an activity invariably exceeds its normal time An activity could be decompressed to the maximum extent of its normal time An activity could be decompressed to the maximum extent of its normal time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT/CPM, techniques can be used for following applications All of these Research and development Maintenance jobs Once through project All of these Research and development Maintenance jobs Once through project ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In inventory control, the economic order quantity is the Optimum lot size Lot corresponding to break-even point Capability of a plant to produce Highest level of inventory Optimum lot size Lot corresponding to break-even point Capability of a plant to produce Highest level of inventory ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Earliest finish time can be regarded as Latest finish time + duration of activity Latest finish time duration of activity Earliest start time + duration of activity Earliest start time duration of activity Latest finish time + duration of activity Latest finish time duration of activity Earliest start time + duration of activity Earliest start time duration of activity ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The mathematical technique for finding the best use of limited resources in an optimum manner is known as Linear programming Break-even analysis Network analysis Operation research Linear programming Break-even analysis Network analysis Operation research ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time All of these It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time All of these It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project ANSWER DOWNLOAD EXAMIANS APP