Industrial Engineering and Production Management Scheduling gives information about That how idle time can be minimized Proper utilization of machines When work should start and how much work should be completed during a certain period When work should complete That how idle time can be minimized Proper utilization of machines When work should start and how much work should be completed during a certain period When work should complete ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In PERT analysis, critical path is obtained by joining events having Zero slack Dummy activities +ve slack -ve slack Zero slack Dummy activities +ve slack -ve slack ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management CPM has following time estimate One time estimate Three time estimate Four time estimate Two time estimate One time estimate Three time estimate Four time estimate Two time estimate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT has following time estimate One time estimate Four time estimate Three time estimate Two time estimate One time estimate Four time estimate Three time estimate Two time estimate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The routing function in a production system design is concerned with Optimizing material flow through the plant Manpower utilization Quality assurance of the product Machine utilization Optimizing material flow through the plant Manpower utilization Quality assurance of the product Machine utilization ANSWER DOWNLOAD EXAMIANS APP