Industrial Engineering and Production Management CPM has following time estimate One time estimate Two time estimate Four time estimate Three time estimate One time estimate Two time estimate Four time estimate Three time estimate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main objective of work measurement is to All of these Estimate the selling prices and delivery dates Plan and schedule of production Formulate a proper incentive scheme All of these Estimate the selling prices and delivery dates Plan and schedule of production Formulate a proper incentive scheme ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If ‘F’ is the fixed cost, ‘V’ is the variable cost per unit (or total variable costs) and ‘P’ is the selling price of each unit (or total sales value), then break-even point is equal to (F × P)/V F/[1 + (V/P)] (F × V)/P F/[1 - (V/P)] (F × P)/V F/[1 + (V/P)] (F × V)/P F/[1 - (V/P)] ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative All of these It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time All of these It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Bin card is used in Workshop Stores Foundry shop Administrative wing Workshop Stores Foundry shop Administrative wing ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A systematic job improvement sequence will consist of All of these Motion study Job enrichment Time study All of these Motion study Job enrichment Time study ANSWER DOWNLOAD EXAMIANS APP