Industrial Engineering and Production Management
Scheduling

Determines the programme for the operations
Prescribes the sequence of operations to be followed
Is concerned with starting of processes
Regulates the progress of job through various processes

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
When slack of an activity is negative

It represents that a programme falls behind schedule and additional resources are required to complete the project in time
All of these
It represents a situation where extra resources are available and the completion of project is not delayed
The activity is critical and any delay in its performance will delay the completion of whole project

ANSWER DOWNLOAD EXAMIANS APP