Industrial Engineering and Production Management Work study is done with the help of Process chart All of the these Material handling Stop watch Process chart All of the these Material handling Stop watch ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Tick the odd man out McGregor Drucker Taylor Galileo McGregor Drucker Taylor Galileo ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Merit Rating is the method of determining worth of Machine A particular division in workshop A job An individual employee Machine A particular division in workshop A job An individual employee ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The assumption in PERT is A project will always be behind schedule, if left uncorrected Activities are fixed and can't be changed A project can be subdivided into a set of predictable, independent activities Cost of project will always be more than the estimated cost, if no timely corrections are taken A project will always be behind schedule, if left uncorrected Activities are fixed and can't be changed A project can be subdivided into a set of predictable, independent activities Cost of project will always be more than the estimated cost, if no timely corrections are taken ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good LS = LFD LF = LS + D EF = ES + D All of these LS = LFD LF = LS + D EF = ES + D All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Father of time study was F.W. Taylor R.M. Barnes F.B. Gilbert H.L. Gantt F.W. Taylor R.M. Barnes F.B. Gilbert H.L. Gantt ANSWER DOWNLOAD EXAMIANS APP