Industrial Engineering and Production Management Queueing theory is used for All of these Inventory problems Traffic congestion studies Job-shop scheduling All of these Inventory problems Traffic congestion studies Job-shop scheduling ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If TL is the largest allowable event occurrence time, total activity slack (s) is equal to Latest finish time earliest finish time (EFT) Latest start time earliest start time TLEFT All of these Latest finish time earliest finish time (EFT) Latest start time earliest start time TLEFT All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Halsey plan of wage incentive Does not guarantee minimum wage Is based upon efficiency of worker Is applied to all level of workers Is not applied to all level of workers Does not guarantee minimum wage Is based upon efficiency of worker Is applied to all level of workers Is not applied to all level of workers ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on: A job evaluation system His individual performance A standard rating system A merit rating system A job evaluation system His individual performance A standard rating system A merit rating system ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main advantage of line organisation is its Rigid discipline in the organisation Defined responsibilities at all levels Effective command and control All of these Rigid discipline in the organisation Defined responsibilities at all levels Effective command and control All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The assumption in PERT is Activities are fixed and can't be changed Cost of project will always be more than the estimated cost, if no timely corrections are taken A project will always be behind schedule, if left uncorrected A project can be subdivided into a set of predictable, independent activities Activities are fixed and can't be changed Cost of project will always be more than the estimated cost, if no timely corrections are taken A project will always be behind schedule, if left uncorrected A project can be subdivided into a set of predictable, independent activities ANSWER DOWNLOAD EXAMIANS APP