Industrial Engineering and Production Management Queueing theory is used for All of these Job-shop scheduling Inventory problems Traffic congestion studies All of these Job-shop scheduling Inventory problems Traffic congestion studies ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Process layout is also known as Static product layout None of these Analytical-layout Synthetic layout Static product layout None of these Analytical-layout Synthetic layout ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Statistical quality control techniques are based on the theory of Probability All of the these Quality Statistics Probability All of the these Quality Statistics ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In CPM, the cost slope is determined by (Normal cost - Crash cost)/ (Normal time - Crash time) Normal Cost/Crash cost (Crash Cost - Normal cost)/ (Normal time - Crash time) Crash cost/Normal Cost (Normal cost - Crash cost)/ (Normal time - Crash time) Normal Cost/Crash cost (Crash Cost - Normal cost)/ (Normal time - Crash time) Crash cost/Normal Cost ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If ‘F’ is the fixed cost, ‘V’ is the variable cost per unit (or total variable costs) and ‘P’ is the selling price of each unit (or total sales value), then break-even point is equal to F/[1 - (V/P)] (F × V)/P (F × P)/V F/[1 + (V/P)] F/[1 - (V/P)] (F × V)/P (F × P)/V F/[1 + (V/P)] ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The assumption in PERT is Cost of project will always be more than the estimated cost, if no timely corrections are taken Activities are fixed and can't be changed A project will always be behind schedule, if left uncorrected A project can be subdivided into a set of predictable, independent activities Cost of project will always be more than the estimated cost, if no timely corrections are taken Activities are fixed and can't be changed A project will always be behind schedule, if left uncorrected A project can be subdivided into a set of predictable, independent activities ANSWER DOWNLOAD EXAMIANS APP