Industrial Engineering and Production Management Routing Is concerned with starting of processes Regulates the progress of job through various processes Prescribes the sequence of operations to be followed Determines the programme for the operations Is concerned with starting of processes Regulates the progress of job through various processes Prescribes the sequence of operations to be followed Determines the programme for the operations ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Work study involves Only work measurement Only motion study Only method study Method study and work measurement Only work measurement Only motion study Only method study Method study and work measurement ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A big advantage of PERT over Gantt charts is that in the former case Interrelationship among activities is clearly shown Early start and late finish of an activity are clearly marked Activities and events are clearly shown Activity times are clear Interrelationship among activities is clearly shown Early start and late finish of an activity are clearly marked Activities and events are clearly shown Activity times are clear ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In value engineering, important consideration is given to Cost reduction Function concept Profit maximization Customer satisfaction Cost reduction Function concept Profit maximization Customer satisfaction ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Tick the odd man out Taylor Drucker Galileo McGregor Taylor Drucker Galileo McGregor ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The assumption in PERT is A project will always be behind schedule, if left uncorrected Activities are fixed and can't be changed Cost of project will always be more than the estimated cost, if no timely corrections are taken A project can be subdivided into a set of predictable, independent activities A project will always be behind schedule, if left uncorrected Activities are fixed and can't be changed Cost of project will always be more than the estimated cost, if no timely corrections are taken A project can be subdivided into a set of predictable, independent activities ANSWER DOWNLOAD EXAMIANS APP