Industrial Engineering and Production Management
The assumption in PERT is

A project can be subdivided into a set of predictable, independent activities
Activities are fixed and can't be changed
A project will always be behind schedule, if left uncorrected
Cost of project will always be more than the estimated cost, if no timely corrections are taken

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
PERT

Permits management to foresee quickly the impact of variations from the plan
Provides a way for management to require that planning be done on a uniform and logical basis
All of the listed here
Provides an approach for keeping planning up-to-date