Industrial Engineering and Production Management Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it Consumes time, but no resources Consumes neither time nor resources Is a dangling event Consumes resources but no time Consumes time, but no resources Consumes neither time nor resources Is a dangling event Consumes resources but no time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following are the guidelines for the construction of a network diagram? Each activity is represented by one and only one arrow in the network Dummy activity consumes no time or resource Dangling must be avoided in a network diagram All of the these Each activity is represented by one and only one arrow in the network Dummy activity consumes no time or resource Dangling must be avoided in a network diagram All of the these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT/CPM, techniques can be used for following applications Once through project All of these Research and development Maintenance jobs Once through project All of these Research and development Maintenance jobs ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management What does symbol 'O' imply in work study? Delay/temporary storage Inspection Transport Operation Delay/temporary storage Inspection Transport Operation ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Critical path moves along the activities having total float of Zero value Same value Negative value Positive value Zero value Same value Negative value Positive value ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management According to MAPI formula, the old machine should be replaced by new one when(Here, CAM = Challenger's Adverse minimum, DAM = Defender's Adverse minimum) There is no such criterion CAM = DAM CAM > DAM CAM < DAM There is no such criterion CAM = DAM CAM > DAM CAM < DAM ANSWER DOWNLOAD EXAMIANS APP