Industrial Engineering and Production Management In PERT analysis, critical path is obtained by joining events having Zero slack +ve slack Dummy activities -ve slack Zero slack +ve slack Dummy activities -ve slack ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Gantt chart provides information about the Material handling Production schedule Proper utilization of manpower Efficient working of machine Material handling Production schedule Proper utilization of manpower Efficient working of machine ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Pessimistic time is The maximum time which an activity might require The most probable time considering all conditions The average time required for a job The minimum time in which an activity can possibly be accomplished The maximum time which an activity might require The most probable time considering all conditions The average time required for a job The minimum time in which an activity can possibly be accomplished ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT has following time estimate One time estimate Four time estimate Three time estimate Two time estimate One time estimate Four time estimate Three time estimate Two time estimate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In the Halsey 50-50 plan, the following are rewarded more All of the these Past poor workers Past good workers Past average workers All of the these Past poor workers Past good workers Past average workers ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In ABC control policy, maximum attention is given to Those items which consume more money Those items which are not readily available Those items which consume money Those × items which are in more demand Those items which consume more money Those items which are not readily available Those items which consume money Those × items which are in more demand ANSWER DOWNLOAD EXAMIANS APP