When slack of an activity is positive

The activity is critical and any delay in its performance will delay the completion of whole project
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
Any one of the above
It represents a situation where extra resources are available and the completion of project is not delayed

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Which of the following are the guidelines for the construction of a network diagram?

Dummy activity consumes no time or resource
Each activity is represented by one and only one arrow in the network
Dangling must be avoided in a network diagram
All of the these

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Which of the following statement is correct about the network diagram?

The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.
The tail end of the arrow represents the start of an activity.
The head of the arrow represents the end of an activity.
All of the these

ANSWER DOWNLOAD EXAMIANS APP