Industrial Engineering and Production Management
When slack of an activity is positive

Any one of the above
It represents a situation where extra resources are available and the completion of project is not delayed
The activity is critical and any delay in its performance will delay the completion of whole project
It represents that a programme falls behind schedule and additional resources are required to complete the project in time

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Pick up the incorrect statement from the following. A critical ratio scheduling

All of the these
Establishes the relative priorities among various activities on a common basis
Adjusts automatically changes in activity progress
Determines the status of each activity

ANSWER DOWNLOAD EXAMIANS APP