Industrial Engineering and Production Management
The assumption in PERT is

Cost of project will always be more than the estimated cost, if no timely corrections are taken
Activities are fixed and can't be changed
A project can be subdivided into a set of predictable, independent activities
A project will always be behind schedule, if left uncorrected