Industrial Engineering and Production Management If TL is the largest allowable event occurrence time, total activity slack (s) is equal to TLEFT Latest finish time earliest finish time (EFT) Latest start time earliest start time All of these TLEFT Latest finish time earliest finish time (EFT) Latest start time earliest start time All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store Inflated system Current value method Fixed price method Primary cost method Inflated system Current value method Fixed price method Primary cost method ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management According to Muther, the basic principle of best layout is Principle of overall integration Principle of flexibility Principle of flow All of the listed here Principle of overall integration Principle of flexibility Principle of flow All of the listed here ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Standard time as compared to normal time is Smaller Equal There is no such correlation Greater Smaller Equal There is no such correlation Greater ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT analysis is based upon All of these Most likely time Pessimistic time Optimistic time All of these Most likely time Pessimistic time Optimistic time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is 100 75 25 50 100 75 25 50 ANSWER DOWNLOAD EXAMIANS APP