Industrial Engineering and Production Management If TL is the largest allowable event occurrence time, total activity slack (s) is equal to Latest start time earliest start time Latest finish time earliest finish time (EFT) All of these TLEFT Latest start time earliest start time Latest finish time earliest finish time (EFT) All of these TLEFT ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A big advantage of PERT over Gantt charts is that in the former case Activity times are clear Early start and late finish of an activity are clearly marked Interrelationship among activities is clearly shown Activities and events are clearly shown Activity times are clear Early start and late finish of an activity are clearly marked Interrelationship among activities is clearly shown Activities and events are clearly shown ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The production cost per unit can be reduced by Producing more with increased inputs Eliminating idle time Producing more with the same inputs Minimizing resource waste Producing more with increased inputs Eliminating idle time Producing more with the same inputs Minimizing resource waste ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be 460 1000 300 500 460 1000 300 500 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is positive It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project Any one of the above It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project Any one of the above It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The start or completion of task is called An event None of these A duration An activity An event None of these A duration An activity ANSWER DOWNLOAD EXAMIANS APP