Industrial Engineering and Production Management If TL is the largest allowable event occurrence time, total activity slack (s) is equal to Latest start time earliest start time TLEFT Latest finish time earliest finish time (EFT) All of these Latest start time earliest start time TLEFT Latest finish time earliest finish time (EFT) All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The routing function in a production system design is concerned with Machine utilization Manpower utilization Optimizing material flow through the plant Quality assurance of the product Machine utilization Manpower utilization Optimizing material flow through the plant Quality assurance of the product ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker On the percentage of standard time On the percentage of time saved Whose output exceeds 67% efficiency On the percentage of time worked On the percentage of standard time On the percentage of time saved Whose output exceeds 67% efficiency On the percentage of time worked ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative All of these The activity is critical and any delay in its performance will delay the completion of whole project It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time All of these The activity is critical and any delay in its performance will delay the completion of whole project It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which one of the following chart gives simultaneously information about the progress of work and machine loading? Gantt chart Process chart Man-machine chart Machine load chart Gantt chart Process chart Man-machine chart Machine load chart ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The appellate authority for an industrial dispute is Management Board of directors High court/supreme court Labour court Management Board of directors High court/supreme court Labour court ANSWER DOWNLOAD EXAMIANS APP