Industrial Engineering and Production Management If TL is the largest allowable event occurrence time, total activity slack (s) is equal to All of these TLEFT Latest start time earliest start time Latest finish time earliest finish time (EFT) All of these TLEFT Latest start time earliest start time Latest finish time earliest finish time (EFT) ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The product layout Lowers overall manufacturing time All of these Utilizes machine and labour better Requires less space for placing machines Lowers overall manufacturing time All of these Utilizes machine and labour better Requires less space for placing machines ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following charts are used for plant layout design? All of these Man machine chart Travel chart Operation process chart All of these Man machine chart Travel chart Operation process chart ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Routing prescribes the Inspection of final product Proper utilization of man power Proper utilization of machines Flow of material in the plant Inspection of final product Proper utilization of man power Proper utilization of machines Flow of material in the plant ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If A is the total items consumed per year, P is the procurement cost per order, and C is the annual inventory carrying cost per item, then the most economic ordering quantity is given by (AP/C)² 2AP/C √(2AP/C) AP/C (AP/C)² 2AP/C √(2AP/C) AP/C ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Earliest finish time can be regarded as Earliest start time duration of activity Latest finish time + duration of activity Earliest start time + duration of activity Latest finish time duration of activity Earliest start time duration of activity Latest finish time + duration of activity Earliest start time + duration of activity Latest finish time duration of activity ANSWER DOWNLOAD EXAMIANS APP