Industrial Engineering and Production Management If TL is the largest allowable event occurrence time, total activity slack (s) is equal to TLEFT Latest finish time earliest finish time (EFT) Latest start time earliest start time All of these TLEFT Latest finish time earliest finish time (EFT) Latest start time earliest start time All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The basic difference between PERT and CPM is that Costs are considered on CPM only and not in PERT Guessed times are used in PERT and evaluated times in CPM PERT deals with events and CPM with activities Critical path is determined in PERT only Costs are considered on CPM only and not in PERT Guessed times are used in PERT and evaluated times in CPM PERT deals with events and CPM with activities Critical path is determined in PERT only ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Basic motion time study gives times for basic motions in ten thousandths of Hour Minute Day Second Hour Minute Day Second ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In the Halsey 50-50 plan, the following are rewarded more Past good workers Past average workers All of the these Past poor workers Past good workers Past average workers All of the these Past poor workers ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management What does symbol 'D' imply in work study? Inspection Transport Delay/temporary storage Permanent storage Inspection Transport Delay/temporary storage Permanent storage ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed All of these The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed All of these ANSWER DOWNLOAD EXAMIANS APP