Airport Engineering Two single runways may be arranged so as to have All listed here L-shape T-shape X-shape All listed here L-shape T-shape X-shape ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering Consider the following statements regarding ICAO recommendation for correction to basic runway length of these statements1. The basic runway length should be increased at the rate of 7 percent per 300 m rise in elevation above the mean sea level.2. The basic runway length after having been corrected for elevation should be further increased at the rate of 1 percent for every 1°C rise in airport reference temperature above the standard atmospheric temperature at that elevation.3. The runway length after having been corrected for elevation and temperature should be further increased at the rate of 20% for every 1 percent of effective gradient. 2 and 3 are correct 1 and 3 are correct 1 and 2 are correct 1, 2 and 3 are correct 2 and 3 are correct 1 and 3 are correct 1 and 2 are correct 1, 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering The length of runway under standard conditions is 2000 m. The elevation of airport site is 300 m. Its reference temperature is 33.05°C. If the runway is to be constructed with an effective gradient of 0.25 percent, the corrected runway length will be 2800 m 2500 m 2600 m 2700 m 2800 m 2500 m 2600 m 2700 m ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering In an airport, if 4 groups of 5 gates each located well separated are considered for traffic and the future to present traffic ratio is 3, then the total requirement of future gates will be 36 68 44 32 36 68 44 32 ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering Assertion A : The ratio of arriving and departing aircrafts influences the airport capacity:Reason R : Landing operation is generally given priority over the taking off operation.Select your answer based on the coding system given below: Both A and R is true and R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true Both A and R is true and R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering For the proposed air port, the survey project provides Master plan Topographic plan Grading plan All listed here Master plan Topographic plan Grading plan All listed here ANSWER DOWNLOAD EXAMIANS APP